Library and park design contract awarded

Summary#

Montréal city council adopted a decision awarding a professional-services contract for the Caroline-Dawson Library and Le Prévost Park project in Villeray–Saint-Michel–Parc-Extension. The goal, as described by city staff, is to provide a larger, modern library and redesign the park; the decision does not award the construction work itself.

  • The contract goes to a team formed by L'OEUF Architectes, Lapointe Magne et associés s.e.n.c.r.l., NIPPAYSAGE inc., Eurêka Environnement, L2C Experts-Conseils inc. and Dupras Ledoux inc.
  • The team must provide design and engineering services, prepare construction tender documents and estimates, support an art competition and choices of furniture and equipment, and prepare “as built” plans. The work also includes specialized services such as resident professional supervision and expertise in forestry, acoustics, lighting and universal access.
  • The city must evaluate the firms’ performance.
  • The decision authorizes contingency and incidentals budgets in addition to the contract. The contract was selected through an architecture competition, not awarded as the lowest-priced bid.

What it means for you#

  • Residents and library users: The decision funds professional services for a new library to replace the current Le Prévost library, and for the redesign of Le Prévost Park. It does not set an opening date or guarantee the proposed sustainability certifications.
  • City: It must pay the contract and authorized budgets, and evaluate the firms’ performance. The decision does not award the construction contract.
  • Taxpayers: The decision authorizes spending, but the materials do not give the full cost of building the library and redesigning the park.

Money#

The resolution’s listed contract and budget amounts total $10,599,257.82, taxes included; the official title gives a different total.

  • Contract: $8,479,406.25, taxes included.
  • Contingencies: $1,271,910.94, taxes included.
  • Incidentals: $847,940.63, taxes included.
  • The title states $10,559,257.81. The three amounts in the resolution add to $10,599,257.82, a difference of $40,000.01.
  • City staff say each finalist was paid $160,000, taxes extra for the competition, and that the winning team’s payment is deducted from its project fees.

What is unclear#

  • No publicly available information in these materials gives the contract’s duration, project completion date, or full construction budget.
  • The materials do not explain how the contingency and incidentals budgets may be used.
  • The project is eligible for a contribution from Québec’s Ministry of Culture and Communications, but the amount and funding arrangements are not given.
  • The materials do not resolve the difference between the title’s total and the sum of the amounts approved in the resolution.

Case for#

  • City staff say the competition was designed to select on quality and creativity, not price alone. The jury chose the team from four finalists after 28 compliant anonymous applications were assessed at the first stage.
  • A multidisciplinary team is responsible for both the library and park design, with specialized expertise included in the contract.
  • The professional services support the city’s stated goals for a modernized library, a redesigned park and environmental certifications.

Case against#

  • Because the competition selected on quality rather than price alone, the materials do not show whether this was the lowest-cost option.
  • The contract and extra budgets authorize substantial spending, while the full construction cost and the amount of any provincial contribution are not stated.
  • The mismatch between the title’s total and the resolution’s itemized amounts makes the total authorization unclear.