City approves park project contingency funding

Summary#

Montréal city council unanimously adopted a decision authorizing more contingency funding for Artelia Canada inc.’s professional services contract to supervise work at parc du Bassin-à-Bois in the Sud-Ouest borough. The additional amount is $153,434.14, taxes included, bringing the contract’s maximum total to $1,917,926.73, taxes included.

  • The original contract was awarded after a public call for tenders with two bidders. The decision summary does not say whether Artelia submitted the lowest compliant bid.
  • The contract’s base value stays at $1,534,341.38. Its contingency budget rises from $230,151.21 to $383,585.35, taxes included.
  • The added funding is for supervision and administrative follow-up through the project’s expected final acceptance in June 2027. Contract hourly rates do not change.

What it means for you#

  • Residents and taxpayers: The City will pay more for professional oversight of the park construction. The decision does not set a new fee or tax rate.
  • Artelia Canada inc.: The firm can receive additional payment for the services covered by the contract, within the revised maximum amount.
  • Park construction: City staff say construction is expected to finish in June 2026, with final acceptance expected in June 2027 after the warranty year.

Money#

The decision authorizes $153,434.14 in additional spending, taxes included.

  • The added cost is $140,105.82 net of TPS and TVQ rebates. The City says it will be paid entirely by the central city through borrowing bylaw 19-039.
  • The added net cost is allocated as $90,000 in 2026 and $50,000 in 2027.
  • The revised maximum contract expense is $1,917,926.73, taxes and contingencies included, or $1,751,322.74 net of rebates.

What is unclear#

  • The materials do not specify how many extra hours or how much work each professional category will provide.
  • They do not describe how the City will track or report use of the added contingency budget.

Case for#

  • City staff say more supervision is needed because the construction schedule has extended. They cite soil contamination requiring twice the planned rehabilitation work, supply delays, a delay in the park’s electrical connection, and subcontractor coordination issues.
  • Staff say the added funding will allow Artelia to continue supervision and administrative follow-up through final acceptance. Hourly rates remain unchanged.

Case against#

  • The contingency budget increases by 67%, from $230,151.21 to $383,585.35, and reaches 25% of the base contract value.
  • A possible concern is that construction delays have increased the City’s oversight costs. The materials do not give a breakdown of the extra hours or say whether further increases may be needed.