City funds borough-led road repairs

Summary#

Montréal city council unanimously approved Mercier–Hochelaga-Maisonneuve borough’s offer to take charge of designing, coordinating and carrying out road and sidewalk rehabilitation on avenue Souligny, between rues Honoré-Beaugrand and Saint-Émile. The decision uses the city’s power under its charter to accept a borough’s offer to provide a service that falls under city council’s responsibility. The stated goal is to carry out repairs on this stretch of the city’s arterial road network.

  • The borough will manage the work, including coordinating required municipal expertise and obtaining required authorizations before construction. It must obtain approvals from the water service, fire service and STM where applicable.
  • The work is mainly road rehabilitation, with minor sidewalk repairs if needed. The city’s road-infrastructure service (SIRR) will pay all project expenses, including design, from available investment budgets.
  • The borough must keep a project budget and schedule, use project funds only for this work, keep its spending within authorized credits, and record expenses separately. It must provide progress updates to the city on request and give the city final plans and profiles when the work is done.
  • City staff scheduled design for spring 2026 and construction for summer and fall 2026. The decision does not award a construction contract.

What it means for you#

  • People using avenue Souligny: The decision enables repairs to the road and, if needed, minor sidewalk repairs. It does not set out a specific construction plan or promise a particular improvement in comfort or safety.
  • Mercier–Hochelaga-Maisonneuve borough: The borough must design, coordinate and carry out the project, subject to the city’s conditions.
  • City taxpayers: The city’s SIRR, not the borough, is responsible for all project costs within available investment budgets. No project cost is stated.

Money#

The city will fund the work from available investment budgets, but the materials give no cost estimate.

  • Road work is assigned to the city’s PCPR–Artériel program; any minor sidewalk repairs are assigned to its PMIR program.
  • The borough must not exceed approved credits without authorization, and must keep the project’s spending separate from its other expenses.
  • The decision gives no contract price, tender results or later returns.

What is unclear#

  • The total budget, final work scope and amount allocated to each part of the project are not stated.
  • The decision does not give details about construction timing beyond the planned seasons, or how residents will be notified about disruptions.
  • It does not set out a public reporting schedule; the borough must report progress to the city only on request.

Case for#

  • City staff say the road has severe early deterioration, including major cracks, multiple potholes and patches.
  • City staff say the borough’s construction expertise and presence in the area make it well placed to deliver the work.
  • Assigning delivery to the borough while the city pays fits the fact that the road is on the city’s arterial network but within the borough.

Case against#

  • The decision commits city investment funds without stating the project’s cost, making the scale of the expense hard to judge.
  • The final extent of sidewalk repairs is uncertain: they are described as minor and only “if needed.”
  • The borough must report to the city on request, but the decision does not specify routine public updates or a fixed reporting schedule.