City approves brake parts framework

Summary#

Montréal’s city council unanimously adopted an orientation to conclude a two-year framework agreement with Chartrand Ford (Ventes) inc. for brake parts for the City’s light and medium vehicles. A framework agreement sets terms for orders placed when needed; the agglomeration council makes the final decision at a later meeting. The stated goal is to keep brake parts available for the City’s vehicle fleet.

  • The proposed agreement has a maximum base amount of $5,179,356, taxes included, plus $1,035,871.20 for contingencies, for a total of $6,215,227.20, taxes included.
  • It includes an option for one 12-month extension. Prices are adjusted annually using an industrial product price index.
  • Chartrand Ford was the only firm to submit a compliant bid in a public call for tenders. The City must evaluate the company’s performance.
  • The City would order parts as needed. It does not promise to buy all listed quantities.

What it means for you#

  • City vehicle service: City staff say the agreement is intended to support a steady supply of brake parts for the Service du matériel roulant et des ateliers (rolling stock and workshops service).
  • Supplier: If the agglomeration council approves the agreement, Chartrand Ford would supply parts on request under its terms. The supplier must provide a manufacturer’s warranty for defects in design and manufacture.
  • Residents and taxpayers: This decision does not directly change residents’ rights, taxes, fees, or services. The City says the spending would come from the workshops’ operating budget.

Money#

The proposed maximum is $6,215,227.20, taxes included; actual orders would depend on the City’s needs.

  • The base agreement is capped at $5,179,356; the separate contingency amount is $1,035,871.20.
  • The decision says spending will be charged to the relevant budgets as needs arise. City staff say the expense has no impact on the City’s financial framework; 5.7% would be paid by the agglomeration.
  • The bid’s base amount was 10.78% below the City’s estimate, but staff say the supplier could not include some items. After removing those items from the estimate, staff report the bid was $102,943.73, or 2.03%, above the adjusted estimate.

What is unclear#

  • The agglomeration council has not yet made the final decision, so it is not yet clear whether the agreement will proceed.
  • The materials do not say how much the City will actually order or spend.
  • The materials do not explain how the contingency funds would be approved or used in specific cases.

Case for#

  • City staff say a framework agreement could help ensure a continuous supply of brake parts needed for vehicle safety and availability.
  • Staff say that without an agreement, the City might need to make individual purchases, which could cause delays and increase costs.
  • Orders based on actual needs mean the City is not committed to buying every listed quantity.

Case against#

  • Only one compliant bid was received, so the materials show no competing compliant offer for comparison.
  • The bid did not include some items in the City’s original estimate; after adjusting for that, the bid was above the adjusted estimate.
  • Annual price adjustments and the contingency provision mean the final spending may vary from the base agreement amount.