Montréal seeks Active Transportation funding

Summary#

Montréal city council adopted a resolution setting the city’s position for an agglomeration council decision on a funding application to the federal Fonds pour le transport actif (Active Transportation Fund). It authorizes the application for five street projects, commits the city to pay its share, and names a city director to sign the contribution agreement and related administrative documents. City staff say the goal is to support safer active-transportation infrastructure; the agglomeration council makes the final decision at a later meeting.

  • The application covers Prieur Est Street (Saint-Firmin Street to the borough limit), de Terrebonne Street (Saint-Ignatius Street to Girouard Street), and Legendre Street (Lajeunesse Street to Meilleur Street).
  • It also covers de l’Esplanade Avenue (Legendre Street to Louvain Street) and Émile-Journault Avenue (Henri-Julien Avenue to Papineau Avenue).
  • The resolution supports these projects and commits Montréal to pay the portion not covered by funding.
  • It does not award federal funding or itself set out detailed construction plans.

What it means for you#

  • People using the five routes: The resolution does not itself change street rules or build infrastructure. If funding is approved and the projects proceed, the routes could receive active-transportation improvements.
  • Montréal taxpayers: The city has committed to fund its share, but the final amount is not set in the resolution.

Money#

The resolution commits the city to pay its share; city staff provide estimates, but no final city cost or federal award is confirmed.

  • Staff estimate eligible expenses of $69,027 for Prieur Est, $64,602 for de l’Esplanade, $54,545 for de Terrebonne, $115,307 for Émile-Journault, and $164,888 for Legendre.
  • The listed maximum federal contributions, at up to 60% of eligible costs, are $41,416, $38,761, $32,727, $69,184, and $98,933, respectively. Together, these are $281,021 from estimated eligible expenses totalling $468,369. The difference is $187,348, but it is not a confirmed final city cost.
  • Staff say the federal program requires funded projects to be completed by March 31, 2030.

What is unclear#

  • The table lists anticipated completion dates of 2023, 2024, or 2025—before this 2026 decision. The materials do not explain those dates or the projects’ current status.
  • The materials do not say whether the federal government will approve funding, or give the final project costs and city contribution.
  • The resolution does not describe the planned designs or construction schedules.

Case for#

  • A possible argument for the decision is that federal funding could cover up to 60% of eligible costs, reducing pressure on the city’s budget for these projects.
  • City staff say the projects are intended to improve conditions for people walking and cycling, improve safety, and, in some cases, add greenery and manage rainwater.

Case against#

  • The city commits to paying the remaining costs, but the final amount is unknown and federal funding is not guaranteed.
  • The past anticipated completion dates make it hard to tell from these materials how ready the projects are or how the funding would be used.