Part IMiscellaneous NoticeVolume 160, Number 35Published: August 29, 2026

TransAlta seeks 30-year hydro licences renewal

Canada Gazette, Part I, Volume 160, Number 35: MISCELLANEOUS NOTICES

TransAlta’s TA Alberta Hydro LP filed to renew water-power licences for the Kananaskis Falls and Horseshoe Falls run‑of‑the‑river plants on the Bow River, requesting a 30-year licence with no changes to the facilities. A 30-day public comment period runs from August 29, 2026 to September 29, 2026, with comments due to the Director responsible for the Dominion Water Power Act at Crown-Indigenous Relations and Northern Affairs Canada.

Published
August 29, 2026
Department
Unavailable
Section
TA ALBERTA HYDRO LP, BY ITS GENERAL PARTNER TA ALBERTA HYDRO INC.
Comment deadline
September 29, 2026
Effective date
Unavailable
Publication part
Part I

Summary

Summary#

TA ALBERTA HYDRO LP, by its general partner TA ALBERTA HYDRO INC. (also called TransAlta), filed an application on October 14, 2024 to renew water-power licences for the Kananaskis Falls and Horseshoe Falls hydroelectric plants under the Dominion Water Power Act. The company asks for a 30-year licence renewal with no changes to the plants; a public comment period runs for 30 days, from August 29, 2026 to September 29, 2026.

What it does#

  • Seeks renewal of water-power licences for Kananaskis Falls and Horseshoe Falls under the Kananaskis Falls and Horseshoe Falls Water Power Regulations (SOR/97-473).
  • Requests a 30-year term for the renewed licences.
  • Confirms both plants are run-of-the-river facilities with generating capacity of 19 MW (Kananaskis) and 16.2 MW (Horseshoe).
  • Says there are no proposed changes to the existing physical facilities or how the plants operate.
  • Opens a 30-day period for comments, starting August 29, 2026 and ending September 29, 2026; comments go to the Director at Crown-Indigenous Relations and Northern Affairs (contact details given in the Gazette notice).

Who's affected#

  • TransAlta customers who get electricity from these plants and people who rely on the local grid in the Bow Valley corridor.
  • Residents and local governments in the Municipal District of Bighorn No. 8 (where the facilities sit).
  • The nearby Stoney Nakoda First Nation Reserves Nos. 142, 143, and 144, because the facilities sit adjacent to those reserves.
  • People and groups concerned with the Bow River — for example, recreational users, anglers, and local environmental organizations — may be interested even though no operational changes are proposed.

Why it matters#

  • A licence renewal for 30 years locks in who can operate these small hydro plants and for how long, affecting long-term electricity supply in the area.
  • The application states there are no changes to the plants or their operations, so the company is not proposing to alter the facilities or how they use the river.
  • The Canada Gazette notice creates a window (from August 29, 2026 to September 29, 2026) for the public and Indigenous communities to raise concerns or objections before a decision is made.
  • Because the facilities are adjacent to Indigenous reserves, the renewal may be of particular interest to local Indigenous communities and any groups monitoring impacts on the river or cultural sites.

Key topics

Dominion Water Power ActKananaskis Falls Water Power Regulations (SOR/97-473)Horseshoe Falls Water Power Regulations (SOR/97-473)Kananaskis Falls hydroelectric facilityHorseshoe Falls hydroelectric facilityrun-of-the-riverTransAlta CorporationTA Alberta Hydro Inc.Bow RiverMunicipal District of Bighorn No. 8Stoney Nakoda First Nation Reserves Nos. 142, 143, 14430-year licence renewalCrown-Indigenous Relations and Northern Affairs Canadapublic comment period

Source: Canada Gazette

Official source