SA 7009. Mr. MORAN (for himself, Mr. Schmitt, Mr. Grassley, and Mr. Young) submitted an amendment intended to be proposed to amendment SA 6883 proposed by Mr. Thune (for Mrs. Capito (for herself, Mr. Lee, Mr. Whitehouse, and Mr. Heinrich)) to the bill H.R. 2347, to amend the Internal Revenue Code of 1986 to exclude from gross income any damages, other than punitive damages, received on account of any sexual acts or sexual contact; which was ordered to lie on the table; as follows:
Text printed in the Record (1,023 characters)
On page 242, strike line 2 and insert the following: the siting of the applicable facility.
"(6) Land restoration.--
"(A) In general.--The Commission shall have the power to attach to the issuance of a permit under subsection (b) such reasonable terms and conditions as the Commission may find necessary to appropriately restore the applicable land following construction.
"(B) Corrective action.--If the holder of a permit issued under subsection (b) fails to comply with any requirement or condition imposed by the Commission that is related to the preservation or restoration of, or mitigation of impacts to, affected property, the Commission shall require corrective action, including through an order requiring corrective action, the costs of which shall be borne by the permit holder.
"(C) Savings provision.--Nothing in this paragraph precludes measures or requirements that differ from those prescribed in this paragraph to protect or restore affected property or to mitigate impacts on such property.".
______
SA 7010. Mr. PAUL submitted an amendment intended to be proposed to amendment SA 6883 proposed by Mr. Thune (for Mrs. Capito (for herself, Mr. Lee, Mr. Whitehouse, and Mr. Heinrich)) to the bill H.R. 2347, to amend the Internal Revenue Code of 1986 to exclude from gross income any damages, other than punitive damages, received on account of any sexual acts or sexual contact; which was ordered to lie on the table; as follows:
Text printed in the Record (88 characters)
Strike section 2116 of the amendment (relating to Transmission Organization governance).
SA 7011. Ms. ALSOBROOKS (for herself and Mrs. Shaheen) submitted an amendment intended to be proposed to amendment SA 6883 proposed by Mr. Thune (for Mrs. Capito (for herself, Mr. Lee, Mr. Whitehouse, and Mr. Heinrich)) to the bill H.R. 2347, to amend the Internal Revenue Code of 1986 to exclude from gross income any damages, other than punitive damages, received on account of any sexual acts or sexual contact; which was ordered to lie on the table; as follows:
Text printed in the Record (11,994 characters)
Strike title II of division A and insert the following:
SEC. 1201. CLEAN WATER ACT PERMITTING AND STATE
CERTIFICATION.
Section 401 of the Federal Water Pollution Control Act (33 U.S.C. 1341) is amended by adding at the end the following:
"(e) Certification Procedures, Requirements, and Limitations.--
"(1) Effect of certain certification actions.--
"(A) Certification or waiver.--If a certifying authority grants a certification application or if a certifying authority waives the certification requirement for a certification application, the agency with jurisdiction over the Federal license or permit for which the certification application was made shall consider water quality requirements satisfied for the purpose of considering the application for the Federal license or permit.
"(B) Certification with conditions.--
"(i) In general.--If a certifying authority grants a certification application with conditions, the agency with jurisdiction over the Federal license or permit for which the certification application was made shall consider water quality requirements satisfied for the purpose of considering the application for the Federal license or permit, subject to the conditions included in the certification.
"(ii) Savings clause.--Nothing in this subparagraph affects paragraph (2)(B).
"(2) Scope of certification.--
"(A) In general.--The scope of a certification provided under this section shall be limited to ensuring that any applicant for a Federal license or permit will comply with water quality requirements with respect to the activity as a whole, including any discharge that may result from the activity.
"(B) Prohibition.--In reviewing a certification application, no certifying authority may--
"(i) deny certification for any reason other than making a determination that--
"(I) no modification to or reasonable condition on the certification would make it possible to grant the certification without violating water quality requirements; or
"(II) after the certifying authority has sent the communication described in clause (v)(II) of paragraph (3)(C) and given the applicant a reasonable opportunity to provide the additional materials or information described in that communication, the application continues to lack--
"(aa) the information required under clause (ii) and, if applicable, clause (iii) of that paragraph; or
"(bb) information needed to evaluate compliance with water quality requirements, as described pursuant to paragraph (3)(D)(iii); or
"(ii) grant certification with conditions, except for conditions that the certifying authority determines are necessary to ensure compliance with water quality requirements.
"(C) Savings provision.--Nothing in this paragraph allows a Federal licensing or permitting agency to refuse to include conditions from a certifying authority in a Federal license or permit if the certifying authority determines the conditions are necessary to ensure compliance with water quality requirements, including conditions applicable to the activity as a whole.
"(D) Rule of construction.--Except as provided in subsection (g), nothing in this section limits the authority of a certifying authority under subsection (d) to establish limitations, conditions, and monitoring requirements applicable to the activity as a whole, rather than solely to the discharge that gives rise to the requirement for certification under subsection (a), if the limitations, conditions, or requirements are necessary to ensure compliance with water quality requirements.
"(3) Required procedures.--
"(A) Notice and hearings.--Taking into account State or Tribal law, as appropriate, and the review period described in paragraph (4), each certifying authority shall establish procedures for--
"(i) public notice in the case of all certification applications;
"(ii) to the extent the certifying authority determines to be appropriate, public hearings in connection with specific certification applications; and
"(iii) a prefiling meeting as described in subparagraph (B).
"(B) Prefiling meeting.--
"(i) Request.--Before submitting a certification application, the prospective applicant may request a prefiling meeting with the certifying authority--
"(I) to ensure that the certifying authority receives early notification of projects for which a certification under subsection (a) is necessary; and
"(II) to discuss informational needs with the certifying authority before submitting the application.
"(ii) Response required.--If a prospective applicant requests a prefiling meeting with a certifying authority pursuant to clause (i), the certifying authority shall--
"(I) respond to the request not later than 30 days after the date on which the request is received; and
"(II) hold the prefiling meeting with the prospective applicant not later than 60 days after the date on which the request is received.
"(C) Certification applications.--
"(i) Application in writing.--A certification application shall be made in writing to the applicable certifying authority.
"(ii) Requirements for complete application.--A complete certification application shall consist of the following:
"(I) Identification of each applicant for the Federal license or permit with respect to which the certification application is made.
"(II) A statement that information included in the certification application is truthful, accurate, and complete, to the best knowledge of each such applicant.
"(III) In the case of a certification application with respect to an individual permit or license--
"(aa) identification of the Federal license or permit that is the subject of the certification application with respect to which the certification is requested;
"(bb) identification of any activity the conduct of which is subject to the Federal license or permit;
"(cc) identification of the location and nature of any discharge that may result from the activity, and the location of the receiving waters;
"(dd) a description of means that may be used to monitor, control, or manage any such discharge; and
"(ee) a list of all other Federal, interstate, Tribal, State, or local agency authorizations related to the requirement for a certification under subsection (a), and any approval or denial of such an authorization already received.
"(IV) Any additional materials required by the applicable certifying authority pursuant to clause (iii), subject to the condition that the additional materials shall only be required with respect to certification applications submitted after the date on which the regulation described in that clause has been promulgated.
"(iii) Additional materials.--
"(I) In general.--A certifying authority may promulgate regulations establishing materials to be required in completed certification applications in addition to the materials described in subclauses (I) through (III) of clause (ii) that the certifying authority determines are necessary to demonstrate to the certifying authority compliance with water quality requirements.
"(II) Requirement.--In promulgating regulations under subclause (I), a certifying authority shall only base the determination regarding what additional materials are needed on what can reasonably be expected of an applicant at the time at which a certification application is submitted.
"(III) Effect of failure to promulgate.--Beginning on or after December 31, 2027, if a certifying authority fails to promulgate regulations under subclause (I), a certification application to that certifying authority shall be considered complete if the certification application includes all of the items described in subclauses (I) through (III) of clause (ii).
"(IV) Transition.--Prior to December 31, 2027, a certifying authority may require materials beyond the materials described in subclauses (I) through (III) of clause (ii) without promulgating regulations under subclause (I) through a single written notice applicable to all applicants submitting certification applications if the certifying authority determines that those additional materials are necessary to demonstrate to the certifying authority compliance with water quality requirements and the additional materials are those that can be reasonably expected of an applicant at the time at which a certification application is submitted.
"(iv) Acknowledgment of receipt.--Not later than 3 days after the date on which an applicant submits to a certifying authority a certification application for an individual Federal license or permit, the certifying authority shall acknowledge receipt of the certification application in writing.
"(v) Notification of complete application or identification of missing materials.--Not later than 90 days after the date on which a certifying authority acknowledges receipt of a certification application under clause (iv), the certifying authority shall--
"(I) provide the applicant a written notification that the certification application is complete; or
"(II) identify to the applicant in writing all specific additional materials or information described in clauses (ii) and, if applicable, (iii) necessary for the certification application to be considered complete, including, for each such additional piece of material or information, a description of the water quality requirement for which the additional material or information is needed in order to evaluate compliance with that water quality requirement.
"(vi) Petition to court.--
"(I) Right to petition.--An applicant may petition for judicial review of an alleged failure by a certifying authority to act in accordance with clauses (ii) through (v) by filing a written petition in a court of competent jurisdiction.
"(II) Considerations.--In reviewing a petition under this subclause, a reviewing court shall consider--
"(aa) the administrative record, which shall consist of the materials required to be submitted under clause (ii);
"(bb) any materials or information identified by certifying authority as missing pursuant to a notification under clause (v)(II);
"(cc) the information submitted by the applicant to the certifying authority; and
"(dd) any evidence presented to the court by the applicant that suggests that the defense of the certifying authority to the petition is pretextual.
"(III) Court order.--If a court, in reviewing a petition under this clause, finds that a certifying authority has failed to act in accordance with any of clauses (ii), (iv), and (v), the court shall provide injunctive relief, as appropriate, to give effect to this section.
"(D) Denials of certification for individual license or permit.--If a certifying authority denies a certification application for an individual license or permit, the certifying authority shall provide to the applicant and the applicable Federal licensing or permitting agency--
"(i) the specific water quality requirements that the certifying authority determined will be violated if certification were granted;
"(ii) a statement explaining why the certifying authority determined the identified water quality requirements will be violated; and
"(iii) if the denial is due to insufficient information, a description of the specific water quality data or information, if any, that would be needed to evaluate whether granting certification will comply with water quality requirements.
"(4) Review period.--
"(A) In general.--Subject to subparagraph (C) and in consultation with each certifying authority, a licensing or permitting agency shall, categorically or on a case-by-case basis for each certification application, establish a reasonable period of time (not to exceed 1 year from the date of receipt of the certification application) within which a certifying authority shall issue a final action on the certification application, which shall account for time required under applicable State or Tribal law for public notice and comment periods, if any.
"(B) Failure to act.--If a certifying authority
Text printed in the Record (11,937 characters)
fails or refuses to issue a final action as described in paragraph (6) on a certification application by the end of the reasonable period of time established under subparagraph (A) and the reasonable period of time has not been extended in accordance with subparagraph (C), the requirement for a certification under subsection (a) shall be waived, except that the reasonable period of time shall restart in the event that the certification application is voluntarily withdrawn by the applicant and the applicant submits a new certification application.
"(C) Requirement for extension.--With respect to a certification application, the reasonable period of time established under subparagraph (A) may only be extended if--
"(i) the extension is requested, in writing, by the applicant; and
"(ii) the certifying authority concurs, in writing, with the extension.
"(5) Waiver of certification requirement.--
"(A) In general.--A certifying authority may, at any time during the reasonable period of time described in paragraph (4), affirmatively waive the requirement for a certification under subsection (a).
"(B) No judicial review.--Notwithstanding any other provision of Federal law, including any provision of this section, a waiver of the requirement for a certification under this section shall not be subject to judicial review.
"(6) Final action.--Not later than the date on which the reasonable period of time established under paragraph (4) for a certification application ends or on the date of a waiver pursuant to paragraph (5)(A), as applicable, the certifying authority shall apply only 1 of the following final actions to the certification application:
"(A) The certification application is granted.
"(B) The certification application is granted with conditions.
"(C) The certification application is denied.
"(D) The certification requirements under subsection (a) have been waived in accordance with paragraph (4) or (5) with respect to the certification application.
"(f) Judicial Review.--
"(1) Burdens of proof.--When reviewing a denial of a certification under this section, a court shall place the burden of proof on the certifying authority to demonstrate that--
"(A) no reasonable modifications to or reasonable conditions on the certification would make it possible to grant the certification without violating water quality requirements; or
"(B) the applicant has not provided information sufficient to evaluate compliance with water quality requirements, as described pursuant to subsection (e)(3)(D)(iii).
"(2) Conditions.--When reviewing a challenge to 1 or more conditions required by a certifying authority under this section, a court shall place the burden of proof on the certifying authority to demonstrate that the 1 or more challenged conditions are necessary to allow the certification to be made without violating water quality requirements.
"(3) Scope of conditions.--A court reviewing a condition required by a certifying authority under this section may not set aside the condition on the basis that the condition applies to the activity as a whole, or to effects of the activity other than the discharge, if the condition is necessary to ensure compliance with water quality requirements.
"(g) Special Rule for Certain Certifications.--
"(1) Definition of interstate transmission line project.--In this subsection, the term `interstate transmission line project' means a project for the construction, modification, or upgrade of a transmission facility that is part of the bulk-power system (as defined in section 215(a) of the Federal Power Act (16 U.S.C. 824o(a))).
"(2) Limitation on certification requirements for certain interstate linear infrastructure.--Notwithstanding the first sentence of subsection (a)(1), any applicant for a certificate of public convenience and necessity for a project under section 7 of the Natural Gas Act (15 U.S.C. 717f) or a Federal authorization or permit required to construct, modify, or operate an interstate transmission line project that may result in a direct point source discharge into the waters of the United States shall provide to the Federal licensing or permitting agency a certification from a certifying authority that such direct point source discharge complies with water quality requirements or a waiver pursuant to this section.
"(3) Certification of no limitation and standard.--In the case of any direct point source discharge described in this subsection for which there is not an applicable effluent limitation or other limitation under sections 301(b) and 302 and for which there is not an applicable standard under sections 306 and 307, the certifying authority shall so certify, except that such a certification shall not satisfy section 511(c).
"(4) Review for compliance.--Notwithstanding subsection (a)(4)--
"(A) prior to the initial operation of any federally licensed or permitted facility or activity that may result in a direct point source discharge into the waters of the United States and with respect to which a certification has been obtained pursuant to this subsection, which facility or activity is not subject to a Federal operating license or permit, the licensee or permittee shall provide an opportunity for the certifying authority to review the manner in which the facility or activity shall be operated or conducted for the purposes of assuring that applicable effluent limitations or other limitations or other applicable water quality requirements will not be violated;
"(B) on notification by the certifying authority that the operation of any federally licensed or permitted facility or activity described in subparagraph (A) will violate applicable effluent limitations or other limitations or other water quality requirements, the applicable Federal agency may, after public hearing, suspend the Federal license or permit; and
"(C) if a Federal license or permit is suspended pursuant to subparagraph (B), the Federal license or permit shall remain suspended until notification is received from the certifying authority that there is reasonable assurance that the facility or activity will not violate the applicable provisions of sections 301, 302, 303, 306, and 307.
"(5) Limitation and monitoring requirements of certain linear infrastructure certifications.--Notwithstanding subsection (d)--
"(A) any certification provided under this subsection shall set forth any effluent limitations and other limitations and monitoring requirements necessary to assure that any direct point source discharge subject to this subsection will comply with the applicable provisions of sections 301, 302, 303, 306, and 307; and
"(B) any limitations and requirements set forth pursuant to subparagraph (A) shall be imposed by the licensing or permitting agency as a condition on any Federal license or permit subject to the provisions of this section.
"(6) Reasonable period of time.--Notwithstanding the periods of time in subsections (a)(1) and (e)(4), a licensing or permitting agency shall, categorically or on a case-by-case basis for each certification application, establish a reasonable period of time (not to exceed 9 months from the date of receipt of the certification application) within which a certifying authority shall issue a final action on the certification application under this subsection, which shall account for the time required under applicable State or Tribal law for public notice and comment periods.
"(h) Definitions.--In this section:
"(1) Certification application.--The term `certification application' means a request from an applicant for a certification described in subsection (a).
"(2) Certifying authority.--The term `certifying authority', with respect to a certification application, means, as applicable--
"(A) the State or interstate agency to which the certification application was submitted, including an Indian Tribe that is treated as a State for purposes of this section pursuant to section 131.8 of title 40, Code of Federal Regulations; or
"(B) if no State or interstate agency has the authority to provide the certification described in subsection (a), the Administrator.
"(3) Water quality requirements.--The term `water quality requirements' means--
"(A) the applicable provisions of sections 301, 302, 303, 306, and 307; and
"(B) any Federal and State or Tribal laws (including regulations) implementing sections 301, 302, 303, 306, and 307, including water quality standards adopted or promulgated under section 303 that include designated uses, water quality criteria, and antidegradation requirements, each of which may be independently enforced through a certification under this section.".
SEC. 1202. PERMIT TERM FOR NPDES PERMITS.
Section 402(b)(1)(B) of the Federal Water Pollution Control Act (33 U.S.C. 1342(b)(1)(B)) is amended by striking "five years" and inserting "7 years".
SEC. 1203. PERMITS FOR DREDGED OR FILL MATERIAL.
(a) Reducing Permitting Uncertainty.--
(1) In general.--Section 404(c) of the Federal Water Pollution Control Act (33 U.S.C. 1344(c)) is amended--
(A) by striking "(c) The Administrator" and inserting the following:
"(c) Specification or Use of Defined Area.--
"(1) In general.--The Administrator";
(B) in paragraph (1) (as so designated), by inserting "during the period described in paragraph (2) and" before "after notice and opportunity for public hearings"; and
(C) by adding at the end the following:
"(2) Period of prohibition.--The Administrator may act pursuant to paragraph (1) only during the period that--
"(A) begins on the date on which an applicant submits a complete application under this section; and
"(B) ends on the date on which the Secretary issues the permit.".
(2) Applicability.--The amendments made by paragraph (1) shall apply to a permit application submitted under section 404 of the Federal Water Pollution Control Act (33 U.S.C. 1344) after the date of enactment of this Act.
(b) Nationwide Permitting Improvement.--Section 404(e) of the Federal Water Pollution Control Act (33 U.S.C. 1344(e)) is amended--
(1) by striking "(e)(1) In carrying" and inserting the following:
"(e) General Permits on State, Regional, or Nationwide Basis.--
"(1) Permits authorized.--In carrying";
(2) in paragraph (2)--
(A) by striking "(2) No general" and inserting the following:
"(2) Term.--
"(A) In general.--No general";
(B) in subparagraph (A) (as so designated), by striking "five years" and inserting "10 years"; and
(C) by adding at the end the following:
"(B) Timing of modification.--The Secretary may modify a general permit pursuant to subparagraph (A) during the term of the general permit or during the renewal of the general permit."; and
(3) by adding at the end the following:
"(3) Considerations.--In determining the environmental effects of an activity under paragraph (1) or (2), the Secretary--
"(A) shall consider only the effects on compliance with water quality requirements (as defined in section 401(h)) of any discharge of dredged or fill material resulting from the activity; and
"(B) shall consider any effects of a discharge of dredged or fill material into less than 2 acres of navigable waters to be a minimal adverse environmental effect.
"(4) Nationwide permits for activities.--
"(A) General permits authorized.--Notwithstanding any other provision of this section, the Secretary shall maintain general permits on a nationwide basis for activities described in subparagraph (B).
"(B) Activities described.--An activity referred to in subparagraph (A) is an activity--
"(i) authorized under Nationwide Permit 12, Nationwide Permit 14, Nationwide Permit 27, Nationwide Permit 43, Nationwide Permit 57, or Nationwide Permit 58, as those nationwide permits are described in and reissued pursuant to the final rule of the Corps of Engineers entitled `Reissuance and Modification of Nationwide Permits' (91 Fed. Reg.
Text printed in the Record (6,840 characters)
768 (January 8, 2026)); and
"(ii) that results in a discharge of dredged or fill material into less than 2 acres of navigable waters for each single and complete project (as defined in section 330.2 of title 33, Code of Federal Regulations (as in effect on the date of enactment of this paragraph), including a single and complete linear project and a single and complete non-linear project (as those terms are defined in the final rule of the Corps of Engineers entitled `Reissuance and Modification of Nationwide Permits' (91 Fed. Reg. 768 (January 8, 2026))).
"(C) Retention of general and individual permitting authority.--Nothing in this paragraph prohibits the Secretary from issuing--
"(i) general permits on a regional or State basis; or
"(ii) individual permits for linear infrastructure projects.
"(5) Reissuance of nationwide permits.--
"(A) In general.--Subject to subparagraph (B), in determining whether to reissue a general permit issued on a nationwide basis under this subsection--
"(i) no consultation with an applicable State pursuant to section 6(a) of the Endangered Species Act of 1973 (16 U.S.C. 1535(a)) is required;
"(ii) no consultation with a Federal agency pursuant to section 7(a)(2) of that Act (16 U.S.C. 1536(a)(2)) is required;
"(iii) the requirements of section 102(2)(C) of the National Environmental Policy Act of 1969 (42 U.S.C. 4332(2)(C)) shall be satisfied by preparing a programmatic environmental assessment with respect to the general permit; and
"(iv) no consultation under section 306108 of title 54, United States Code, is required.
"(B) Requirement.--Clauses (i) through (iv) of subparagraph (A) shall only apply to a general permit being reissued pursuant to that subparagraph if the general permit does not--
"(i) narrow or eliminate preconstruction requirements; or
"(ii) raise the threshold for such preconstruction requirements.".
SEC. 1204. JUDICIAL REVIEW TIMELINE CLARITY.
Section 404 of the Federal Water Pollution Control Act (33 U.S.C. 1344) is amended--
(1) in subsection (t), by striking "(t) Nothing in this section" and inserting the following:
"(u) Savings Provision.--Nothing in this section"; and
(2) by inserting after subsection (s) the following:
"(t) Judicial Review.--
"(1) Statute of limitations.--Notwithstanding any applicable provision of law relating to statutes of limitations--
"(A) an action seeking judicial review, under subchapter II of chapter 5, and chapter 7, of title 5, United States Code (commonly known as the `Administrative Procedure Act'), or any other applicable provision of law, of the approval by the Administrator of a State permit program pursuant to this section shall be filed not later than the date that is 150 days after the date on which the approval was issued, unless a shorter time period is otherwise provided for by law;
"(B) an action seeking judicial review, under subchapter II of chapter 5, and chapter 7, of title 5, United States Code (commonly known as the `Administrative Procedure Act'), or any other applicable provision of law, of an individual permit or general permit issued under this section shall be filed not later than the date that is 150 days after the date on which the permit was issued, unless a shorter time period is otherwise provided for by law; and
"(C) an action seeking judicial review, under subchapter II of chapter 5, and chapter 7, of title 5, United States Code (commonly known as the `Administrative Procedure Act'), or any other applicable provision of law, of a verification that an activity involving a discharge of dredged or fill material is authorized by a general permit issued under this section shall be filed not later than the date that is 150 days after the date on which the verification was issued, unless a shorter time period is otherwise provided for by law.
"(2) Limitation on commencement of certain actions.--
"(A) In general.--Notwithstanding any other provision of law but subject to subparagraph (B), no action described in subparagraph (A) or (B) of paragraph (1) may be commenced unless the action--
"(i) is filed by a party that submitted a comment--
"(I) during the public comment period for the administrative proceedings related to the action; and
"(II) that is sufficiently detailed to put the Administrator, the Secretary, or the State, as applicable, on notice of the issue on which the party seeks judicial review; and
"(ii) is related to that comment.
"(B) Limitation.--The limitation under subparagraph (A) shall only apply to actions for which--
"(i) a draft of the action was published in the Federal Register; and
"(ii)(I) the applicable agency provided a public comment period of not less than 30 days; and
"(II) such public comment period occurred after the date of enactment of the Bipartisan American Affordability and Jobs Act of 2026.
"(3) Remedies for actions relating to permits.--If a court determines that the Secretary or a State, as applicable, did not comply with the requirements of this section in issuing an individual or general permit under this section, or in verifying that an activity involving a discharge of dredged or fill material is authorized by a general permit issued under this section, or otherwise was arbitrary and capricious under subchapter II of chapter 5, and chapter 7, of title 5, United States Code (commonly known as the `Administrative Procedure Act'), as applicable--
"(A) the court shall remand the matter to the Secretary or the State, as applicable, for further proceedings consistent with the determination of the court;
"(B) with respect to a determination regarding the issuance of an individual or general permit under this section, the court
may not vacate, revoke, enjoin, or otherwise limit the permit unless the court finds that activities authorized under the permit would present an imminent and substantial danger to human health or the environment for which there is no other equitable remedy available under the law; and
"(C) with respect to a determination regarding a verification that an activity involving a discharge of dredged or fill material is authorized by a general permit issued under this section, the court may not enjoin or otherwise limit the discharge unless the court finds that the activity would present an imminent and substantial danger to human health or the environment for which there is no other equitable remedy available under the law.
"(4) Timeline to act on court order.--If a court remands a matter under paragraph (3), the court shall set and enforce a reasonable schedule and deadline, which may not exceed 180 days from the date on which the court remands the matter, except as otherwise required by law, for the Administrator, the Secretary, or the State, as applicable, to take such actions as the court may order.".
______
SA 7012. Mr. OSSOFF (for himself and Mr. Warnock) submitted an amendment intended to be proposed to amendment SA 7005 submitted by Mr. Ossoff (for himself and Mr. Warnock) and intended to be proposed to the amendment SA 6883 proposed by Mr. Thune (for Mrs. Capito (for herself, Mr. Lee, Mr. Whitehouse, and Mr. Heinrich)) to the bill H.R. 2347, to amend the Internal Revenue Code of 1986 to exclude from gross income any damages, other than punitive damages, received on account of any sexual acts or sexual contact; which was ordered to lie on the table; as follows:
Text printed in the Record (9,990 characters)
On page 1 of the amendment, strike lines 13 and 14 and insert the following:
(f) Accelerated Permitting for Projects Using Domestic Content.--
(1) Prioritization.--In processing applications, assigning agency personnel and resources, and scheduling environmental reviews and other required agency actions for eligible projects that produce or store electricity from solar (referred to in this subsection as "eligible solar projects") pursuant to this section, the Secretary of the Interior or the Secretary of Agriculture, as applicable, shall give priority under paragraph (3) to such projects that qualify under paragraph (2).
(2) Domestic content certification.--
(A) In general.--An eligible solar project shall qualify for priority treatment under paragraph (3) if an applicant submits to the Secretary of the Interior or the Secretary of Agriculture, as applicable, a certification that a project is expected, when placed into service, to satisfy the domestic content requirements described in section 48E(a)(3)(B) of the Internal Revenue Code of 1986 as of the date of enactment of this Act (irrespective of whether the credit is claimed or available to be claimed), including applicable regulations and guidance.
(B) Application.--
(i) In general.--An applicant seeking priority treatment under paragraph (3) for an eligible solar project shall submit to the Secretary of the Interior or the Secretary of Agriculture, as applicable, a certification at such time, in such manner, and containing such information as the Secretary of the Interior or the Secretary of Agriculture, as applicable, may require, including--
(I) a good faith commitment, explaining that the applicant shall commit to ensuring that, once placed into service, the eligible solar project will satisfy the requirements described in subparagraph (A);
(II) at the discretion of the applicant, a demonstration of expected compliance with the requirements described in subparagraph (A) using the domestic content requirements, methodologies, or elective safe harbors established by the Secretary of the Treasury, including those applicable to repowered facilities; and
(III) any other information the Secretary of the Interior or the Secretary of Agriculture, as applicable, may require.
(ii) Limitation.--Except for the requirements described in clause (i), no Federal agency may impose any additional domestic content, documentation, review, or other approval requirement as a condition to receive priority treatment under paragraph (3).
(C) Notice to agencies.--
(i) In general.--Not later than 10 days after receiving a certification under subparagraph (A), the Secretary of the Interior or the Secretary of Agriculture, as applicable, shall transmit that certification to each applicable Federal agency responsible for an action subject to a deadline under paragraph (3).
(ii) Clarification.--Failure by the Secretary of the Interior or the Secretary of Agriculture, as applicable, to transmit a certification under clause (i) shall not delay, restart, or extend any deadline under paragraph (3).
(iii) Applicant transmission.--An applicant that submits a certification under subparagraph (A) may transmit that certification to each applicable Federal agency responsible for an action subject to a deadline under paragraph (3).
(3) Expedited federal reviews and authorizations.--
(A) Reduced deadlines.--In the case of an eligible solar project that is the subject of a certification submitted under paragraph (2), the deadlines for completion of an environmental assessment or environmental impact statement, an issuance of a finding of no significant impact or record of decision, and issuance of decisions on outstanding authorizations under subparagraphs (A) and (B) of section 107(g)(1) of the National Environmental Policy Act of 1969 (42 U.S.C. 4336a(g)(1)) for that project shall be reduced by 50 percent, subject to the condition that--
(i) a period expressed in days shall be rounded up to the next whole day; and
(ii) a period expressed in years shall be converted to months before applying the reduction.
(B) Applicability.--
(i) In general.--A reduced deadline under subparagraph (A) shall apply to each Federal agency responsible for an action subject to the deadline.
(ii) Public comment.--Each Federal agency shall comply with both the reduced deadline and any applicable public comment or participation requirement.
(iii) Effective date.--A reduced deadline under subparagraph (A) shall apply to the deadlines described in that subparagraph in accordance with the effective date and applicability provisions otherwise governing those deadlines.
(C) Judicial enforcement.--
(i) In general.--A reduced deadline under subparagraph (A) shall be enforceable, as applicable--
(I) under section 107(g) of the National Environmental Policy Act of 1969 (42 U.S.C. 4336a(g));
(II) as if the reduced deadline was a deadline under subsection (b)(1) of section 1403 and as if the application was a covered application (as defined under subsection (a) of that section).
(ii) Application.--All procedures, exceptions, burdens of proof, expedited review, venue provisions, and remedies under the applicable provision described in clause (i), including injunctive relief, orders compelling agency action, and retained jurisdiction, shall apply as those procedures, exceptions, burdens of proof, expedited review, venue provisions, and remedies apply to the underlying deadline.
(D) Completion and records.--
(i) Completion.--Not later than 90 days after an eligible solar project is placed into service, an applicant that received priority treatment under this paragraph shall submit to the Secretary of the Interior or the Secretary of Agriculture, as applicable, a certification explaining that, as applicable--
(I) the eligible solar project has satisfied all the requirements of paragraph (2)(A); or
(II) the eligible solar project has not satisfied all the requirements of paragraph (2)(A), including the level of noncompliance.
(ii) Records.--An applicant that received priority treatment under this paragraph shall--
(I) retain records sufficient to substantiate any certification required under this paragraph for a period of not less than 3 years after the eligible solar project is placed into service; and
(II) make the records required under subclause (I) available, on request, to the Secretary of the Interior or the Secretary of Agriculture, as applicable.
(4) Verification.--
(A) In general.--The Secretary of the Interior or the Secretary of Agriculture, as applicable, shall consider a certification submitted under paragraph (2)(A) as sufficient to establish eligibility for priority without an independent determination of domestic content compliance under that paragraph, subject to the condition that the Secretary of the Interior or the Secretary of Agriculture, as applicable, shall subsequently verify the accuracy of the certification using only the domestic content methodologies established by the Secretary of the Treasury.
(B) Inclusions.--Verification under subparagraph (A) may include a review of the completion certification and supporting records required under paragraph (2)(B), including after placement into service.
(C) Delay.--Verification under subparagraph (A) shall not delay an environmental review or other Federal agency action.
(5) Loss of priority.--
(A) In general.--An eligible solar project shall cease to qualify for priority treatment under paragraph (3) if, before issuance of the final Federal authorization or permit required for the eligible solar project--
(i) the applicant withdraws the certification submitted under paragraph (2)(A); or
(ii) the Secretary of the Interior or the Secretary of Agriculture, as applicable, determines, in writing, through verification under paragraph (4), that--
(I) the certification materially misrepresented the expected compliance of the eligible solar project at the time the certification was submitted; or
(II) the eligible solar project is no longer reasonably expected to satisfy the applicable domestic content requirements described in paragraph (2).
(B) Determination.--A determination under subparagraph (A)(ii) shall--
(i) describe the basis for its findings; and
(ii) be reviewable by any action under paragraph (3)(C).
(C) Effect.--
(i) In general.--A loss of priority treatment under subparagraph (A) shall apply--
(I) prospectively only; and (II) from the date--
(aa) of withdrawal by the applicant under subparagraph (A)(i); or
(bb) a determination is made under subparagraph (A)(ii).
(ii) Impact.--
(I) In general.--Loss of priority treatment under subparagraph (A) shall not--
(aa) invalidate any prior Federal agency action or issued Federal authorization or permit;
(bb) restart any review period;
(cc) by itself constitute grounds for denying, suspending, modifying, or revoking an issued Federal authorization or permit; or
(dd) relieve an applicant that received any priority treatment of the completion certification and record keeping requirements under paragraph (3)(D).
(II) Reduced deadline.--
(aa) Expired.--For any action on the eligible solar project with a reduced deadline that expired before the applicable date described in clause (i)(II), that deadline shall remain enforceable under paragraph (3)(C).
(bb) Not expired.--For any action on the eligible solar project with a reduced deadline that has not yet expired, the deadline that shall apply is the deadline that would have otherwise been applicable if not for the reduced deadline required under paragraph (3), to be measured from the date on which it would otherwise have begun.
(6) Rule of construction.--Nothing in this subsection shall--
(A) shorten any period for public comment or participation, alter any deadline applicable to judicial proceedings, or waive or alter any substantive requirement of the National Environmental Policy Act of 1969 (42 U.S.C.
Text printed in the Record (5,583 characters)
4321 et seq.) or any other applicable Federal law;
(B) require approval of any Federal authorization or permit;
(C) extend any deadline otherwise applicable to an eligible solar project;
(D) make an eligible solar project ineligible for consideration because the applicant does not seek priority treatment under paragraph (3); or
(E) limit any right, protection, procedure, cause of action, or remedy otherwise available to an eligible solar project, applicant, or project sponsor under this Act or any other applicable Federal law.
(7) Civil penalty for material misrepresentation.--
(A) In general.--An applicant that knowingly or recklessly makes a material misrepresentation in a certification submitted under paragraph (2)(A) or (3)(D) shall be liable to the United States for a civil penalty in an amount equal to 2 percent of the total costs of construction, subject to subparagraph (C), for the applicable eligible solar project.
(B) Inclusion.--In subparagraph (A), a material misrepresentation includes a certification made without a reasonable factual basis if the applicant knowingly or recklessly disregarded facts material to the expected satisfaction of the applicable domestic content requirements described in paragraph (2).
(C) Incomplete projects.--
(i) In general.--If construction of the eligible solar project has not been completed on the date on which an action under subparagraph (E) is commenced, the total construction costs under subparagraph (A) shall be determined from costs incurred and reasonably documented projected costs of completing the eligible solar project, excluding land acquisition, financing, and operation costs.
(ii) Abandonment.--If the eligible solar project has been permanently abandoned, as determined by the Secretary of the Interior or the Secretary of Agriculture, as applicable, the total construction costs under subparagraph (A) shall consist only of costs actually incurred through abandonment by the applicant.
(D) Responsible entities.--
(i) In general.--An entity that knowingly directed or participated in conduct described in subparagraph (A) may be held jointly and severally liable with the applicant for the applicable civil penalty required under that subparagraph.
(ii) Establishment.--For the purposes of clause (i), common ownership or affiliation, by itself, shall not establish liability under that clause.
(E) Enforcement.--
(i) Referral.--The Secretary of the Interior or the Secretary of Agriculture, as applicable, may refer a matter under this paragraph to the Attorney General to bring in an appropriate district court of the United States a civil action to collect a civil penalty under this paragraph.
(ii) Civil action.--In a civil action brought under clause (i)--
(I) the Attorney General shall establish a violation described in subparagraph (A) and the amount of the penalty by a preponderance of the evidence;
(II) the applicant shall provide, to the extent reasonably available, a statement of total construction costs; and
(III) if the applicant fails to provide a statement of total construction costs under subclause (II), the court may determine costs from other available and reliably evidence.
(iii) Limitations period.--An action brought under this subparagraph shall be commenced not later than 3 years after the latest of--
(I) the date a certification is submitted by the applicant under paragraph (2)(A);
(II) the date a certification is submitted by the applicant under paragraph (3)(D).
(F) Effect on authorizations.--A civil penalty or finding of misrepresentation arising solely under this paragraph shall not--
(i) invalidate a previously issued Federal authorization or permit;
(ii) require the suspension of construction or operation of an eligible solar project;
(iii) be treated as fraud, intentional concealment, or material misrepresentation in obtaining a Federal authorization or permit for the purposes of section 1401(b)(1)(C); or
(iv) except with respect to a deadline reduced under paragraph (3), be treated as fraud or material misrepresentation for the purposes of--
(I) paragraph (4)(C)(iv) of section 107(g) of the National Environmental Policy Act of 1969 (42 U.S.C. 4336a(g)); or
(II) section 1403(d)(3).
(G) Effect on other law.--Subject to subparagraph (F), nothing in this paragraph limits any other applicable Federal law.
(8) Report.--Not later than 30 days after the end of each quarter beginning after the date of enactment of this Act, the Secretary of the Interior and the Secretary of Agriculture shall each submit to the Committees on Energy and Natural Resources and Agriculture, Nutrition, and Forestry of the Senate, and the Committees on Natural Resources and Agriculture of the House of Representatives a report, that includes--
(A) the number of eligible solar projects for which priority treatment was requested, granted, and terminated under this subsection;
(B) the processing times for eligible solar projects that received priority treatment compared to other eligible solar projects that did not receive priority treatment, including compliance with the reduced deadlines required under paragraph (3);
(C) the results of any verification conducted under paragraph (4); and
(D) a qualitative assessment of whether priority treatment provided under this subsection is supporting domestic manufacturing, which shall include a recommendation on whether the Secretary of the Interior or the Secretary of Agriculture, as applicable, should continue to provide priority treatment under this subsection.
______
SA 7013. Mr. WELCH submitted an amendment intended to be proposed to amendment SA 6883 proposed by Mr. Thune (for Mrs. Capito (for herself, Mr. Lee, Mr. Whitehouse, and Mr. Heinrich)) to the bill H.R. 2347, to amend the Internal Revenue Code of 1986 to exclude from gross income any damages, other than punitive damages, received on account of any sexual acts or sexual contact; which was ordered to lie on the table; as follows:
Text printed in the Record (1,423 characters)
Beginning on page 169 of the amendment, strike line 22 and all that follows through page 170, line 3, and insert the following:
(1) Covered project or action.--
(A) In general.--The term "covered project or action" means a project or action with a non-Federal project sponsor that has secured all necessary Federal authorizations or permits for construction or operation.
(B) Exclusion.--The term "covered project or action" does not include a project or action related to the construction or operation of a data center or high-density computing facility.
(2) Data center or high-density computing facility.--
(A) In general.--The term "data center or high-density computing facility" means a facility, or group of colocated facilities, the primary purpose of which is to house computing, networking, or data storage equipment used to process, store, or transmit digital data, including equipment used for--
(i) artificial intelligence training or inference;
(ii) cloud computing or data hosting; or
(iii) cryptocurrency mining or other distributed-ledger or digital-asset computation.
(B) Exclusion.--The term "data center or high-density computing facility" does not include computing or data storage equipment that is ancillary to a facility the primary purpose of which is a commercial or industrial activity other than an activity described in subparagraph (A).
(3) Federal authorization or permit.--
______
SA 7014. Mr. WELCH submitted an amendment intended to be proposed to amendment SA 6883 proposed by Mr. Thune (for Mrs. Capito (for herself, Mr. Lee, Mr. Whitehouse, and Mr. Heinrich)) to the bill H.R. 2347, to amend the Internal Revenue Code of 1986 to exclude from gross income any damages, other than punitive damages, received on account of any sexual acts or sexual contact; which was ordered to lie on the table; as follows:
Text printed in the Record (6,372 characters)
Beginning on page 181 of the amendment, strike line 22 and all that follows through page 187, line 16, and insert the following:
(2) Data center or high-density computing facility.--
(A) In general.--The term "data center or high-density computing facility" means a facility, or group of colocated facilities, the primary purpose of which is to house computing, networking, or data storage equipment used to process, store, or transmit digital data, including equipment used for--
(i) artificial intelligence training or inference;
(ii) cloud computing or data hosting; or
(iii) cryptocurrency mining or other distributed-ledger or digital-asset computation.
(B) Exclusion.--The term "data center or high-density computing facility" does not include computing or data storage equipment that is ancillary to a facility the primary purpose of which is a commercial or industrial activity other than an activity described in subparagraph (A).
(3) Federal authorization or permit.--The term "Federal authorization or permit" means an authorization, permit, record of decision, right-of-way, finding of no significant impact, verification, extension, construction and operations plan, biological opinion, incidental take statement, variance, departure, determination, concurrence, or any other similar approval or order that is necessary, including any determination by a Federal department or agency that additional authorizations or permits are not necessary, for the construction or operation at normal capacity of a specific type of covered project.
(4) Pattern of disparate treatment.--The term "pattern of disparate treatment" means, with respect to 1 specific type of covered project, an empirically demonstrated statistical pattern that--
(A) shows a substantial increase, compared against the 10 most recent calendar years of empirical data on Federal authorization or permit decisions and delays for that specific type of covered project, in--
(i) the percentage of Federal authorizations or permits for that 1 specific type of covered project that are unreasonably delayed beyond the applicable timeline as described in subsection (d)(1)(A)(ii); or
(ii) the percentage of Federal authorizations or permits for that 1 specific type of covered project that are denied;
(B) persists--
(i) for a Federal authorization or permit for which an environmental impact statement or environmental assessment (as those terms are defined in section 3 of the National Environmental Policy Act of 1969) are not required, over a minimum period of 180 days, at least 180 days of which occurred after the date of enactment of this Act; or
(ii) for a Federal authorization or permit for which an environmental impact statement or environmental assessment (as so defined) are required, over a minimum period of 280 days, at least 280 days of which occurred after the date of enactment of this Act; and
(C) is the result of an intentional course of action undertaken by the Federal Government to create such a pattern.
(5) Specific type of covered project.--
(A) In general.--The term "specific type of covered project" means 1 of the following types of projects:
(i) A project to produce electricity from onshore wind.
(ii) A project to produce electricity from offshore wind.
(iii) A project to produce electricity from solar.
(iv) An energy storage project.
(v) A project to produce electricity from coal.
(vi) A project to produce electricity from natural gas.
(vii) A project to produce electricity from oil.
(viii) A project to produce electricity from a nuclear fission reactor.
(ix) A project to produce electricity from geothermal.
(x) An onshore electricity transmission project.
(xi) An offshore electricity transmission project.
(xii) A natural gas pipeline project.
(xiii) An oil pipeline project.
(xiv) A hydrogen pipeline project.
(xv) A carbon dioxide pipeline project.
(xvi) A natural gas liquids pipeline project.
(xvii) A project to produce coal.
(xviii) A project to produce onshore natural gas.
(xix) A project to produce offshore natural gas.
(xx) A project to produce onshore oil.
(xxi) A project to produce offshore oil.
(xxii) A hardrock mining project to produce minerals, with hardrock mining projects that produce the same mineral to be considered the same specific type of covered project for purposes of this subparagraph.
(xxiii) A hardrock mineral processing project to produce or expand production of hardrock minerals.
(xxiv) A project to produce electricity from hydrogen.
(xxv) A project to produce electricity from biomass.
(xxvi) A project to refine or process petroleum products.
(xxvii) A project to produce biomass.
(xxviii) A hydropower project.
(xxix) A pumped storage hydropower project.
(xxx) A project to produce electricity from a fusion machine.
(xxxi) A project to produce uranium.
(xxxii) A project to enrich, convert, fabricate, reprocess, or store source material or special nuclear material (as those terms are defined in section 11 of the Atomic Energy Act of 1954 (42 U.S.C. 2014)).
(xxxiii) A project to export or import liquefied natural gas.
(xxxiv) A project to liquefy natural gas or to regasify liquefied natural gas.
(xxxv) A project to export or import crude oil.
(xxxvi) A project to export or import refined petroleum products.
(xxxvii) A project to export or import coal.
(xxxviii) A geologic carbon dioxide sequestration or storage project, including an injection well.
(xxxix) An enhanced oil or natural gas recovery project, including a project using carbon dioxide, water, or other injectants.
(xl) Long-duration battery storage.
(xli) A project to refine or process crude oil.
(xlii) A project to refine natural gas or natural gas liquids.
(xliii) An ammonia pipeline project.
(xliv) A produced water pipeline project.
(xlv) A helium pipeline project.
(xlvi) A coal gasification project.
(xlvii) Any other specific type of energy related project not described in clauses (i) through (xlvi) that a United States district court of competent jurisdiction certifies shares common industrial characteristics, taking into account the specificity of the covered project types described in clauses (i) through (xlvi).
(B) Exclusion.--The term "specific type of covered project" does not include a data center or high-density computing facility project.
______
SA 7015. Mr. BENNET submitted an amendment intended to be proposed to amendment SA 6957 submitted by Mr. Bennet (for himself, Mr. Schiff, and Mr. Lujan) and intended to be proposed to the amendment SA 6883 proposed by Mr. Thune (for Mrs. Capito (for herself, Mr. Lee, Mr. Whitehouse, and Mr. Heinrich)) to the bill H.R. 2347, to amend the Internal Revenue Code of 1986 to exclude from gross income any damages, other than punitive damages, received on account of any sexual acts or sexual contact; which was ordered to lie on the table; as follows:
Text printed in the Record (11,991 characters)
Beginning on page 1 of the amendment strike line 3 and all that follows through page 35, line 20, and insert the following:
(2) Tribal programs.--
(A) In general.--Chapter 3027 of title 54, United States Code, is amended by adding at the end the following:
"Sec. 302707. Tribal program support and coordination
"(a) Self-determination.--
"(1) In general.--A tribal historic preservation program approved under section 302702 shall be considered an exercise of the inherent governmental authority of the Indian tribe.
"(2) Written consent.--Nothing in this section authorizes the Secretary to assume, reassign, or perform functions of a Tribal Historic Preservation Officer without the express written consent of the governing body of the applicable Indian tribe.
"(b) Technical Assistance.--At the request of an Indian tribe, the Secretary, in consultation with the Tribal Historic Preservation Officer, shall provide technical assistance, training, and capacity support to promote timely and effective administration of the tribal historic preservation program.
"(c) Existing Audits.--
"(1) In general.--An audit satisfying section 5 of the Indian Self-Determination and Education Assistance Act (25 U.S.C. 5305) shall satisfy any fiscal-audit requirement applicable to funds provided for a tribal historic preservation program.
"(2) No additional program evaluation.--No additional recurring program evaluation or fiscal audit of a tribal historic preservation program may be required solely by reason of approval of a tribal historic preservation program under section 302702.
"(d) Due Process; No Takeover.--
"(1) Definition of covered deficiency.--In this subsection, the term `covered deficiency' means an alleged material misuse of Federal funds by a tribal historic preservation program.
"(2) Requirements.--Before withholding funds from a tribal historic preservation program for a covered deficiency, the Secretary shall--
"(A) provide to the tribal historic preservation program written notice of the covered deficiency;
"(B) identify the specific covered deficiency of the tribal historic preservation program in the notice provided under subparagraph (A);
"(C) offer technical assistance to tribal historic preservation program; and
"(D) allow not less than 2 years to cure the specific covered deficiency identified under subparagraph (B).
"(3) Narrowly tailored remedy.--Any remedy of the Secretary under paragraph (2) with respect to a covered deficiency under that paragraph--
"(A) shall be narrowly tailored to the affected funds; and
"(B) shall not include Federal assumption of Tribal Historic Preservation Officer functions.".
(3) Conforming amendment.--Section 302702 of title 54, United States Code, is amended, in the matter preceding paragraph (1), by striking "302302 and 302303" and inserting "302303 and 302707".
(4) Clerical amendment.--The table of sections for chapter 3027 of title 54, United States Code, is amended by adding at the end the following:
"302707. Tribal program support and coordination.".
(b) Effect of Undertaking on Historic Property.--Section 306108 of title 54, United States Code, is amended--
(1) in the second sentence, by striking "The head of the Federal agency" and inserting the following:
"(2) Opportunity to comment.--The head of any Federal agency described in paragraph (1)";
(2) in the first sentence, by striking "The head of any Federal agency having direct or indirect" and inserting the following:
"(b) Adverse Effect of the Undertaking.--
"(1) In general.--The head of any Federal agency having direct";
(3) by inserting before subsection (b) (as so designated) the following:
"(a) Definitions.--In this section:
"(1) Adverse effect of the undertaking.--
"(A) In general.--The term `adverse effect of the undertaking' means a consequence of an undertaking that--
"(i) is reasonably foreseeable; and
"(ii) directly or indirectly alters the characteristics of a historic property in a manner that would diminish the integrity of the location, design, setting, materials, workmanship, or association of the historic property.
"(B) Exclusions.--The term `adverse effect of the undertaking' does not include--
"(i) any visual, atmospheric, or audible element, unless the visual, atmospheric, or audible element would directly or indirectly diminish the eligible characteristics of the historic property or the integrity of a property of traditional religious or cultural importance;
"(ii) any temporary alteration to a historic property that is limited to the time it takes to complete an undertaking, unless the temporary alteration would directly or indirectly diminish the integrity of a property of traditional religious or cultural importance; or
"(iii) any effect on a portion of the historic property other than an adverse effect to the character-defining features, including contributing elements, cultural-use locations, or access points, that do not contribute to the qualification of the property for inclusion on the National Register.
"(2) Area of potential effects.--
"(A) In general.--The term `area of potential effects' means the area within which an undertaking may cause an effect described in paragraph (1)(A).
"(B) Exclusion.--The term `area of potential effects' does not include any geographic area affected solely by a portion of a project, activity, or program that is not subject to substantial Federal control and responsibility.
"(3) Made public.--The term `made public', with respect to a final agency action, means that the final agency action is published in a single location on the primary website of the applicable Federal agency with--
"(A) hyperlinks to the final agency action prominently displayed on the website; and
"(B) the date of initial publication of the final agency action displayed and maintained on the website.
"(4) Reasonably foreseeable.--
"(A) In general.--The term `reasonably foreseeable', with respect to an adverse effect of the undertaking, means an effect of the undertaking that shares a reasonably close causal relationship to, and is proximately caused by, the undertaking being considered.
"(B) Exclusions.--The term `reasonably foreseeable', with respect to an adverse effect of the undertaking, does not include--
"(i) any adverse effect of the undertaking that is speculative or attenuated from the undertaking; or
"(ii) any adverse effect of the undertaking that--
"(I) relates to an unrelated prior, separate existing, or potential future undertaking; and
"(II) is not foreseeable.
"(5) State historic preservation officer.--The term `State Historic Preservation Officer' means--
"(A) the official designated and appointed pursuant to section 302301(1) to administer the State Historic Preservation Program; or
"(B) a representative designated to act for the official described in subparagraph (A).
"(6) Substantial federal control and responsibility.--The term `substantial Federal control and responsibility' means the ability of the Federal official to modify or condition the project, activity, or program in a manner that avoids, minimizes, or mitigates adverse effects of the undertaking on a historic property.
"(7) Tribal historic preservation officer.--The term `Tribal Historic Preservation Officer' means the Tribal official designated pursuant to section 302702(2) who has assumed the duties of the State Historic Preservation Officer for purposes of compliance with subsection (b) within the boundaries of the applicable tribal land.
"(8) Undertaking.--
"(A) In general.--The term `undertaking' means a project, activity, or program that--
"(i) requires a Federal permit, license, or approval; and
"(ii) is subject to substantial Federal control and responsibility.
"(B) Exclusion.--The term `undertaking' does not include--
"(i) any portion of a project, activity, or program over which a Federal agency does not exercise substantial control or responsibility;
"(ii) a project, activity, or program for which the only Federal involvement is a loan, loan guarantee, grant (including a capitalization grant), cost-share award, or other form of financial assistance that is not for the primary purpose of historic preservation, subject to the condition that this clause shall not apply to a project that--
"(I) receives more than $10,000,000 of financial assistance from the Department of Transportation; or
"(II) would directly or indirectly diminish the integrity of a property of traditional religious or cultural importance;
"(iii) a project, activity, or program that consists of minor or routine restoration, rehabilitation, repair, maintenance, stabilization, hazardous material remediation, structure hardening, provision of handicapped access, or other similar minor or routine projects that do not diminish the integrity of a historic property, unless the project, activity, or program would directly or indirectly diminish the integrity of a property of traditional religious or cultural importance;
"(iv) a project, activity, or program that is a survey or work completed to conduct consultations;
"(v) unless the project, activity, or program would directly or indirectly diminish the integrity of a property of traditional religious or cultural importance, a project, activity, or program that--
"(I) is any alteration to a historic property that is necessary for public safety; and
"(II) does not diminish the integrity of the historic property;
"(vi) an activity or decision that is non-discretionary and made in accordance with the statutory authority of the Federal agency;
"(vii) any--
"(I) renewal of a special use permit on the expiration of the special use permit if no substantive changes are made from the original special use permit; or
"(II) transfer of ownership of a special use permit;
"(viii) the implementation of, or any act or omission under, a memorandum of agreement, programmatic agreement, or other instrument executed in connection with compliance with this section, after the date on which a determination has been made under subsection (c); or
"(ix) the continuation, operation, maintenance, or post-approval implementation of a project, activity, or program after the determination has been made under subsection (c), except that a subsequent discrete decision of a Federal agency to amend or materially modify a determination made under subsection (c) is itself an undertaking, to the extent provided in this section."; and
(4) by adding at the end the following:
"(c) Consultation.--
"(1) In general.--The responsibilities of a Federal agency under this section shall be limited to historic properties within the area of potential effects identified by the Federal agency.
"(2) Initiation and report.--
"(A) Determination.--
"(i) In general.--Not later than 30 days after the date of receipt of a request for review of a proposed project, activity, or program under this section, the applicable Federal official shall determine whether the proposed project, activity, or program is an undertaking subject to the requirements of this section.
"(ii) Applicability of other provisions.--Subject to paragraph (7)(B)(ii), if the review of an undertaking is governed by a Federal agency program alternative established under section 800.14 of title 36, Code of Federal Regulations (or a successor regulation), or this section, including an alternate procedure, programmatic agreement, exempted category, standard treatment, or program comment, the applicable Federal official shall carry out this paragraph in accordance with that program alternative, subject to paragraph (4), subparagraphs (A) and (B) of paragraph (5), and paragraph (6).
"(B) Report on undertaking.--
"(i) In general.--If the applicable Federal official determines under subparagraph (A) that the proposed project, activity, or program is an undertaking, the applicable Federal official shall prepare a report that includes a preliminary assessment of the
Text printed in the Record (8,234 characters)
following:
"(I) A determination regarding the area of potential effects for the undertaking.
"(II) The dentification of any historic properties within the area of potential effects.
"(III) A description of the adverse effects, if any, of the undertaking on historic properties within the area of potential effects.
"(ii) Mandatory solicitation of information.--On making a determination under subparagraph (A)(i), the applicable Federal official shall seek, discuss, and incorporate information from each applicable State Historic Preservation Officer, Tribal Historic Preservation Officer, Indian tribe, or Native Hawaiian organization, local government, and project, activity, or program applicant, if the information is communicated to the applicable Federal official not later than 90 days after the date on which the Federal official submits a request for such information.
"(iii) Consultation.--
"(I) In general.--If the applicable Federal official determines under subparagraph (A) that a proposed project, activity, or program is an undertaking that is not subject to subparagraph (A)(ii), not later than 60 days after
the date of the determination under subparagraph (A), the applicable Federal official shall complete the report in accordance with subclause (II) and initiate consultation on the preliminary assessment by submitting the report for review to the applicable State Historic Preservation Officer, Tribal Historic Preservation Officer, Indian tribe, Native Hawaiian organization, local government, and project, activity, or program applicant under this division.
"(II) Requirements.--A complete report under this clause--
"(aa) shall identify the area of potential effects for the undertaking;
"(bb) shall identify whether any historic properties are present within the applicable area of potential effects;
"(cc) if a historic property is present within the area of potential effects, shall--
"(AA) consider only the portion of the property within the area of potential effects;
"(BB) document any adverse effects of the undertaking, or determine that the proposed project, activity, or program is an undertaking for which there are no adverse effects of the undertaking; and
"(CC) identify prudent and feasible measures within the area of potential effects to avoid, minimize, or mitigate any adverse effects of the undertaking; and
"(dd) shall not identify measures described in item (cc)(CC) that are not prudent or would occur outside the area of potential effects, unless the project, activity, or program applicant has submitted a written request for alternative mitigation measures.
"(3) Determination.--
"(A) In general.--Not later than 90 days after the date of submission of a report under paragraph (2)(B)(iii)(I), unless a shorter timeline is agreed to by the State Historic Preservation Officer or Tribal Historic Preservation Officer and each applicable Indian tribe, Native Hawaiian organization, and local government, the applicable Federal official, in consultation with the applicable State Historic Preservation Officer and Tribal Historic Preservation Officer, Indian tribe, Native Hawaiian organization, and local government under this division, shall--
"(i) determine, based on the report, that--
"(I)(aa) historic properties are not present; and
"(bb) the obligations of the applicable Federal official under this section shall be satisfied; or
"(II)(aa) there are no adverse effects of the undertaking that would diminish the integrity of the historic property to the extent that the historic property would be made ineligible for listing on the National Register; and
"(bb) the obligations of the Federal official under this section shall be satisfied; or
"(ii) reach an agreement with the applicable State Historic Preservation Officer and Tribal Historic Preservation Officer, Indian tribe, Native Hawaiian organization, local government, and project, activity, or program applicant that describes how the adverse effects of the undertaking would be avoided, minimized, or mitigated.
"(B) No agreement.--
"(i) Consultation period.--If an agreement is not reached under clause (ii) of subparagraph (A) within the 90-day period described in that subparagraph, during the 60-day period beginning immediately after the end of that 90-day period, there shall be a period of consultation among the applicable Federal official, State Historic Preservation Officer and Tribal Historic Preservation Officer, Indian tribe, Native Hawaiian organization, and local government.
"(ii) Formal advisory comments.--
"(I) Request.--If an agreement is not reached under clause (i) within the 60-day period described in that clause, the head of the Federal agency shall request formal advisory comments from the Council with respect to the applicable undertaking.
"(II) Response.--Not later than 45 days after the date on which the Council receives a request under subclause (I), the Council shall submit to the head of the Federal agency the formal advisory comments requested.
"(III) Final determination.--Not later than 30 days after the date on which the head of the Federal agency receives the formal advisory comments from the Council under subclause (II), the head of the Federal agency (or an agency official delegated by the head of the Federal agency) shall make a final determination on the undertaking that demonstrates how the formal advisory comments were considered.
"(IV) Satisfaction of obligations.--Effective on the date on which a final determination is made under subclause (III), the obligations of the applicable Federal agency under this section shall be satisfied.
"(C) Multiple determinations.--If an undertaking involves multiple corridors or large land areas, the applicable Federal official may issue multiple determinations under subparagraph (A) in a phased process.
"(4) Lead federal agency.--
"(A) In general.--If more than 1 Federal agency has jurisdiction over a project, activity, or program that is determined to be an undertaking, the 1 or more applicable Federal agencies shall designate a lead Federal agency to comply with the requirements of this subsection.
"(B) Presumption.--If a lead Federal agency has been designated for purposes of complying with the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.), the lead Federal agency designated for purposes of complying with that Act shall serve as the lead Federal agency for purposes of this subsection unless the applicable Federal agencies jointly determine that another Federal agency is better suited to carry out the responsibilities of the lead Federal agency under this subsection.
"(C) Written request; designation by secretary.--If the 1 or more applicable Federal agencies do not designate a lead Federal agency under subparagraph (A) by the date that is 15 days after the date on which the applicable Federal agencies receive notice of a proposed undertaking--
"(i) in the case of an undertaking initiated by an applicant, the applicant may submit to the Secretary a written request for the Secretary to designate a lead Federal agency; or
"(ii) in the case of an undertaking initiated by the Federal Government, the Secretary shall designate a lead Federal agency.
"(D) Failure to sign programmatic agreement.--The failure of the head of a Federal agency that is not the lead Federal agency to be a signatory to a programmatic agreement under this subsection shall not affect the conduct of the project, activity, or program subject to the programmatic agreement.
"(5) Timelines for consultation.--
"(A) Initiation.--If a project, activity, or program requires the preparation of an environmental document under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.), any consultation with respect to the project, activity, or program required for purposes of this subsection shall initiate not later than the date of initiation of the environmental review.
"(B) Completion.--
"(i) In general.--The consultation process initiated under subparagraph (A) shall be completed not later than the date on which the applicable environmental document under section 107(g) of the National Environmental Policy Act of 1969 (42 U.S.C.
Text printed in the Record (11,216 characters)
4336a(g)) is completed with respect to the undertaking, unless the Secretary approves an extension of the deadline due to extraordinary circumstances beyond the control, and not due to any actions, of the consulting parties.
"(ii) Failure to complete by deadline.--If the consultation process initiated under subparagraph (A) is not complete by the later of the deadline established under clause (i) or the date extended under that clause, the consultation requirement for purposes of this subsection, each employee within the Senior Executive Service (as defined in section 2101a of title 5) that has supervisory authority over personnel in a relevant Federal agency that has a substantive role or responsibility in the consultation, shall spend not less than 50 percent of the workweek, as determined pursuant to title 5 or other applicable law, to remedy the failure.
"(iii) Causes of action.--
"(I) Right to petition.--A project, activity, or program applicant may obtain judicial review of the compliance by a Federal agency with the deadline established under clause (i) by filing a complaint with a court of competent jurisdiction in which a substantial part of the applicable proposed project, activity, or program is situated.
"(II) Remedy.--If a court of competent jurisdiction under this clause finds that a Federal agency has failed to act in accordance with this subsection, the court shall--
"(aa) provide injunctive relief, as appropriate, to give effect to this subsection;
"(bb) retain jurisdiction to ensure compliance with any such relief; and
"(cc) set a schedule and deadline for the Federal agency to act as soon as practicable with respect to the injunctive relief, which shall not exceed 90 days from the date on which the applicable order of the court is issued.
"(III) Expedited procedures; time to decide.--The reviewing court under this clause shall--
"(aa) establish an expedited schedule for briefing and disposition; and
"(bb) issue a decision as expeditiously as practicable, but not later than 120 days, after the date on which the applicable complaint is filed under subclause (I), absent extraordinary circumstances.
"(C) Participation of state historic preservation officer or tribal historic preservation officer.--
"(i) In general.--If the State Historic Preservation Officer, Tribal Historic Preservation Officer, Indian tribe, Native Hawaiian organization, or local government fails to respond within 30 days, or 90 days, if paragraph (6) applies, of receipt of a request for review of any report or finding by the applicable Federal official, the applicable Federal official shall proceed to the determination under paragraph (3)(A).
"(ii) Subsequent involvement.--If a State Historic Preservation Officer, Tribal Historic Preservation Officer, Indian tribe, Native Hawaiian organization, or local government that fails to respond by the deadline described in clause (i) re-enters the consultation process required for purposes of this subsection, the applicable Federal official--
"(I) shall not be required to reconsider any previous report or finding; and
"(II) may consult with the Council in lieu of the State Historic Preservation Officer or Tribal Historic Preservation Officer.
"(iii) No substantive objections.--If the State Historic Preservation Officer, Tribal Historic Preservation Officer, Indian tribe, Native Hawaiian organization, local government, or Council, as applicable, has entered the consultation process required for purposes of this subsection, but does not provide any substantive objections by the date on which the consultation period concludes, the
applicable Federal official shall proceed to the determination under paragraph (3)(A).
"(iv) Substantive objections.--If the State Historic Preservation Officer, Tribal Historic Preservation Officer, Indian tribe, Native Hawaiian organization, local government, or Council, as applicable, has entered the consultation process required for purposes of this subsection and provides substantive objections or other information with respect to any of the matters included in the applicable report under subitems (AA) through (DD) of paragraph (2)(B)(iii)(II)(cc) by the date on which the consultation period concludes, not later than 30 days after the date of receipt of the objections or information, the applicable Federal official--
"(I) shall provide a response explaining how the Federal agency has considered the substantive objections or information in the report; and
"(II) may provide a supplemental report.
"(v) Fulfillment of consulting obligations.--On the provision of a response under clause (iv)(I), the obligation of the applicable Federal official to consult for purposes of this subsection shall be considered to be fulfilled with respect to the report.
"(vi) Agreement.--If a State Historic Preservation Officer or Tribal Historic Preservation Officer fails to respond to an agreement under this subparagraph, the applicable Federal official may enter into the agreement with the Council in lieu of the State Historic Preservation Officer or Tribal Historic Preservation Officer.
"(vii) Notice of final agency action.--For any undertaking for which a report under paragraph (2)(B) is required, the applicable Federal official that completed the report and conducted consultation pursuant to that paragraph shall notify, as applicable, each applicable State Historic Preservation Officer, Tribal Historic Preservation Officer, Indian tribe, Native Hawaiian organization, and local government of the final agency action with respect to which the report was prepared.
"(6) Tribally identified historic property.--
"(A) Notice.--
"(i) In general.--At any time before final agency action, an Indian tribe, Tribal Historic Preservation Officer, or Native Hawaiian organization may provide written notice that an undertaking may affect any potential property of traditional religious or cultural importance to the Indian tribe or Native Hawaiian organization.
"(ii) Requirement.--A notice under clause (i) shall identify the potential historic property and the nature of the concern with as much specificity as the Indian tribe, Tribal Historic Preservation Officer, or Native Hawaiian organization determines can be provided, consistent with the protection of sensitive information.
"(B) Effect.--On receipt of a notice under subparagraph (A)--
"(i) each otherwise applicable 30-day period for an Indian tribe, Tribal Historic Preservation Officer, or Native Hawaiian organization to provide information, review, respond, or object under this section shall be 90 days for the Indian tribe, Tribal Historic Preservation Officer, or Native Hawaiian organization;
"(ii) the agency shall promptly provide the Indian tribe, Tribal Historic Preservation Officer, or Native Hawaiian organization with the preliminary analysis or consideration by the agency of the undertaking description, maps, area of potential effects, identification materials, effect findings, and proposed avoidance, minimization, or mitigation measures;
"(iii) the agency shall engage in consultation with the Indian tribe, Tribal Historic Preservation Officer, or Native Hawaiian organization to resolve the concerns raised in the Tribal notification, including consultation between the head of the agency or an Assistant Secretary-level designee and the elected Tribal leadership (or a designee) immediately on Tribal notification;
"(iv) the failure to identify the resource before initiation of review shall not waive the consideration of information timely submitted under subparagraph (A); and
"(v) the agency shall protect information identified by the Indian tribe, Tribal Historic Preservation Officer, or Native Hawaiian organization as sensitive to the maximum extent permitted under section 307103 and any other applicable law.
"(C) Judicial review; preliminary injunction.--For a claim brought by an Indian tribe, Tribal Historic Preservation Officer, or Native Hawaiian organization concerning a resource identified under subparagraph (A)--
"(i) the limitations period under subclause (I) of paragraph (9)(D)(i) shall be 300 days after the later of the dates specified in items (aa) and (bb) of that subclause; and
"(ii) a court may issue a preliminary injunction to the Indian tribe, Tribal Historic Preservation Officer, or Native Hawaiian organization.
"(D) Rule of construction.--This paragraph--
"(i) establishes minimum additional time for Tribal review; and
"(ii) does not limit the authority of an agency to provide a longer period or to extend consultation by agreement.
"(7) Coordination with nepa.--For any undertaking subject to the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.), the applicable Federal official may use the preparation of a draft environmental document that the Federal agency prepares under that Act to comply with the report required under paragraph (2)(B) if the applicable Federal official--
"(A) has notified each applicable State Historic Preservation Officer or Tribal Historic Preservation Officer, Indian tribe, Native Hawaiian organization, local government, and the Council of the intent to use the environmental document for that purpose; and
"(B) determines that the draft environmental document includes each of the components required to be in the report under paragraph (2)(B).
"(8) Program alternatives.--
"(A) By federal agency.--The head of any Federal agency shall, in consultation with the Council, develop and implement program alternatives, including an alternate procedure, programmatic agreement, exempted category, standard treatment, or program comment, to govern categories of undertakings that are--
"(i) determined to normally have no adverse effects of the undertaking;
"(ii) similar and repetitive in nature; or
"(iii) routine management activities undertaken at Federal installations, facilities, or other land management units.
"(B) By state and tribal historic preservation officers.--
"(i) In general.--A State Historic Preservation Officer or a Tribal Historic Preservation Officer may develop and implement program alternatives similar to those developed by Federal agencies under section 800.14 of title 36, Code of Federal Regulations (or a successor regulation), including an alternate procedure, programmatic agreement, exempted category, standard treatment, or program comment, within their applicable jurisdiction to govern categories of undertakings that are--
"(I) determined to normally have no adverse effects of the undertaking; or
"(II) similar and repetitive in nature.
"(ii) Multiple program alternatives.--If a Federal program alternative is developed under section 800.14 of title 36, Code of Federal Regulations (or a successor regulation), and a State Historic Preservation Officer or Tribal Historic Preservation Officer develops a program alternative under clause (i) to govern the same type of undertakings, the Federal agency shall apply the State or Tribal program alternative, unless the applicable State Historic Preservation Officer or Tribal Historic Preservation Officer agrees to the application of the Federal program alternative.
______
SA 7016. Mr. WELCH submitted an amendment intended to be proposed to amendment SA 6883 proposed by Mr. Thune (for Mrs. Capito (for herself, Mr. Lee, Mr. Whitehouse, and Mr. Heinrich)) to the bill H.R. 2347, to amend the Internal Revenue Code of 1986 to exclude from gross income any damages, other than punitive damages, received on account of any sexual acts or sexual contact; which was ordered to lie on the table; as follows:
Text printed in the Record (11,653 characters)
Strike section 2108 of the amendment and insert the following:
SEC. 2108. DISPATCHABLE ENERGY SYSTEMS MARKET ACCESS.
(a) Definitions.--Section 3 of the Federal Power Act (16 U.S.C. 796) is amended by adding at the end the following:
"(30) Qualifying behind-the-meter distributed energy system facility; qualifying BTM DES facility.--The term `qualifying behind-the-meter distributed energy system facility' or `qualifying BTM DES facility' means a facility that--
"(A) is an energy storage system (including a battery energy storage system), a fuel cell system, a generator, or other resource (including an energy efficiency or demand response resource) that can be dispatched, adjusted, or curtailed at a signal by the system operator;
"(B) is located behind the meter of a retail customer of a distribution utility (as defined in section 217(a)); and
"(C) if the facility is a generating or injecting resource, maintains metering and telemetry capabilities that--
"(i) are sufficient to dispatch the facility, account for withdrawals from and injections to the grid, and communicate all relevant operational data from the facility; and
"(ii) with the exception of advanced metering infrastructure necessary to facilitate the participation of energy efficiency and demand response resources, are not required to include equipment owned or installed by the distribution utility (as so defined), and may include the use of device-level equipment, including inverters.
"(31) Qualifying behind-the-meter distributed energy system aggregation; qualifying BTM DES aggregation.--The term `qualifying behind-the-meter distributed energy system aggregation' or `qualifying BTM DES aggregation' means an aggregation of 2 or more qualifying BTM DES facilities--
"(A) with a combined capacity of not less than 100 kilowatts; and
"(B) that maintains aggregation-level metering and telemetry capabilities, where the particular wholesale market requires such capabilities, sufficient to facilitate the dispatch and market settlement of the aggregation.".
(b) Rule of Construction.--Section 201 of the Federal Power Act (16 U.S.C. 824) is amended by adding at the end the following:
"(h) Qualifying BTM DES Facilities and Aggregations.--The designation of a facility as a qualifying BTM DES facility or an aggregation of 2 or more facilities as a qualifying BTM DES aggregation does not, of itself, subject any of the following to the jurisdiction of the Commission:
"(1) The facility or aggregation.
"(2) The retail electric service provided to or for the facility or aggregation.
"(3) The distribution service on which the facility or aggregation relies.".
(c) Wholesale Market Access for Qualifying BTM DES Aggregations.--Part II of the Federal Power Act (16 U.S.C. 824 et seq.) (as amended by section 2107(b)) is amended by adding at the end the following:
"SEC. 229. WHOLESALE MARKET ACCESS FOR QUALIFYING BTM DES
AGGREGATIONS.
"(a) Definitions.--In this section:
"(1) Commission.--The term `Commission' means the Federal Energy Regulatory Commission.
"(2) Double compensation.--The term `double compensation' means payment through or by both a wholesale market and a State-jurisdictional retail market or program for providing the same service during the same time interval.
"(b) Just and Reasonable Practices.--Effective on the date that is 18 months after the date of enactment of this section, it shall not be just and reasonable within the meaning of sections 205 and 206 for any Transmission Organization to maintain rates, terms, or conditions of service that, by their terms and to the extent that such rates, terms, and conditions directly affect wholesale rates, prevent the participation of any qualifying BTM DES aggregation in wholesale energy, capacity, or ancillary services markets administered by the Transmission Organization.
"(c) Prohibited Practices.--The following practices shall not be considered to be just and reasonable within the meaning of sections 205 and 206:
"(1) Imposing metering, telemetry, or equipment requirements that are inconsistent with the definitions of the terms `qualifying BTM DES facility' and `qualifying BTM DES aggregation' in section 3.
"(2) Requiring a qualifying BTM DES facility or qualifying BTM DES aggregation to participate in the energy market as a precondition to participating in the capacity market.
"(3) Requiring the joint participation with any resource co-located with a Qualifying BTM DES facility as a condition for inclusion in a qualifying BTM DES aggregation.
"(4) Any other practice otherwise described in subsection (b).
"(d) Compliance Filings.--
"(1) Transmission organization filings.--Not later than 180 days after the date of enactment of this section, each Transmission Organization that administers a wholesale market subject to the jurisdiction of the Commission shall file with the Commission proposed rates, terms, and conditions of service that comply with the requirements of this section.
"(2) Commission action.--Not later than 180 days after the filing of a proposal under paragraph (1), the Commission shall--
"(A) approve the proposal if the Commission determines that the proposal complies with this section; or
"(B) require or impose such changes as the Commission determines to be just, reasonable, and in compliance with this section.
"(e) Complaints.--
"(1) In general.--The Commission shall act on the merits of any complaint alleging noncompliance with this section not later than 180 days after the date on which the complaint is filed.
"(2) Consolidation.--To maximize administrative efficiency, the Commission may consolidate and act upon related complaints with respect to a given Transmission Organization.
"(f) Dual Participation; Prohibition on Double Compensation.--
"(1) Preservation of state program eligibility.--Participation by a qualifying BTM DES facility in a State-jurisdictional retail market or program shall not disqualify the qualifying BTM DES facility from participating in a wholesale market administered by a Transmission Organization, and nothing in this section requires a qualifying BTM DES facility to participate in any wholesale market.
"(2) Prohibition on double compensation.--No qualifying BTM DES facility or qualifying BTM DES aggregation shall receive double compensation.
"(3) Qualifying btm des rate filing.--
"(A) In general.--Not later than 180 days after the date of enactment of this section, each Transmission Organization shall file with the Commission under section 205 revisions to its tariff establishing settlement, metering, and telemetry protocols that exclude from wholesale market settlement the quantity of energy, ancillary service, or capacity, evaluated on a service-by-service basis, for which a qualifying BTM DES facility has received or will receive compensation under a State-jurisdictional retail market or program, such that, for example, a BTM DES facility that has earned retail energy credit but not ancillary services or capacity credit may receive wholesale compensation for capacity and ancillary services without receiving any wholesale energy compensation.
"(B) Electric utilities.--Each public utility that provides distribution service to a qualifying BTM DES facility shall provide to the applicable Transmission Organization and aggregator, in a form and on a schedule established by the Transmission Organization, accurate interval metering data, customer and premises data, and all program-participation information reasonably necessary to participate in wholesale markets, subject to such protections for customer-specific information as the applicable State commission may require.
"(C) Certification.--
"(i) In general.--Each aggregator shall certify to the applicable Transmission Organization, on a schedule established by the Commission--
"(I) each State-jurisdictional retail market or program from which each qualifying BTM DES facility has received compensation; and
"(II) on the basis of final determinations made by the Commission arising from the proceedings initiated under subparagraph (A), that no qualifying BTM DES facility in its aggregation has retained double compensation during the certification period.
"(ii) Treatment.--A certification under this subparagraph shall constitute a statement made to the Commission for purposes of sections 316 and 316A.
"(4) Complaint with respect to double compensation.--
"(A) In general.--Any person, electric utility, State, municipality, or State commission aggrieved by alleged double compensation may file a complaint pursuant to section 206.
"(B) Procedure.--In a proceeding initiated pursuant to a complaint under subparagraph (A), if a qualifying BTM DES facility or qualifying BTM DES aggregation that is the subject of the complaint meets the eligibility requirements of both a wholesale market and a State-jurisdictional program, the complainant in that proceeding shall--
"(i) bear the burden of proof before the Commission; and
"(ii) demonstrate that--
"(I) double compensation has in fact occurred or is imminent; and
"(II) such double compensation could not be avoided through reasonable adjustments to--
"(aa) wholesale market compensation received by the applicable qualifying BTM DES facility or qualifying BTM DES aggregation; or
"(bb) the retail bill associated with the qualifying BTM DES facility or qualifying BTM DES aggregation, using metering and telemetry data that meets the requirements of the wholesale market.
"(C) Limitation.--A complaint under subparagraph (A) shall be filed not later than 5 years after the date on which the alleged double compensation was received.
"(5) Wholesale market compensation adjustment.--If the Commission determines that double compensation could be avoided through an adjustment to a rate, term, or condition of service under the jurisdiction of the Commission pursuant to section 205, the Commission may initiate a proceeding consistent with section 206 to eliminate double compensation.
"(6) Disgorgement; penalties.--
"(A) Disgorgement.--If the Commission finds that double compensation has occurred, the Commission shall order disgorgement of the full amount of the double compensation received.
"(B) Penalties.--If the Commission determines that double compensation has been knowingly retained, the Commission may order penalties, which may include--
"(i) monetary penalties of up to 3 times the amount of the double compensation received for each day that the double compensation was knowingly retained after the date of receipt, without regard to the limitations described in section 206(b); and
"(ii) suspension or termination of the participation of a qualifying BTM DES facility, qualifying BTM DES aggregation, or aggregator in a wholesale market administered by a Transmission Organization.
"(g) Annual Reporting.--Each qualifying BTM DES facility and qualifying BTM DES aggregation participating in a wholesale market under this section shall submit to the Commission, not later than March 30 of each year, a public report that summarizes and quantifies all services provided by the qualifying BTM DES facility or qualifying BTM DES aggregation during the preceding calendar year to--
"(1) wholesale markets subject to the jurisdiction of the Commission; and
"(2) State-jurisdictional retail markets and programs within regions subject to the jurisdiction of the Commission.".
(d) Distribution Utility Interconnection and Noninterference.--Part II of the Federal Power Act (16 U.S.C. 824 et seq.) (as amended by subsection (c)) is amended by adding at the end the following:
"SEC. 230.
Text printed in the Record (9,084 characters)
DISTRIBUTION UTILITY OBLIGATIONS WITH RESPECT TO
QUALIFYING BTM DES FACILITIES AND QUALIFYING
BTM DES AGGREGATIONS.
"(a) Definitions.--In this section:
"(1) Commission.--The term `Commission' means the Federal Energy Regulatory Commission.
"(2) Distribution utility; load-serving entity.--The terms `distribution utility' and `load-serving entity' have the meanings given those terms in section 217(a).
"(b) Interconnection Obligation.--
"(1) In general.--Except as otherwise provided by State law or by the State regulatory authority with jurisdiction over the distribution utility, any distribution utility
located within the geographic footprint of an organized wholesale market administered by a Transmission Organization shall interconnect any behind-the-meter resource that is eligible to participate in that wholesale market, including any qualifying BTM DES facility or qualifying BTM DES aggregation, in a timely fashion and with rates, terms, and conditions of service that--
"(A) allow the behind-the-meter resource to export energy to the grid, if applicable; and
"(B) do not prevent, impede, or unreasonably condition the participation of the behind-the-meter resource in the wholesale market.
"(2) Savings provision.--Nothing in this subsection authorizes the Commission to prescribe the rates, terms, or conditions of distribution-level interconnection service.
"(c) Acceptance of Wholesale Market Metering Data.--
"(1) In general.--Any distribution utility or load-serving entity providing retail electric service to a customer at whose premises a qualifying BTM DES facility or qualifying BTM DES aggregation is located shall accept the same metering and telemetry data used by the wholesale market for purposes of market participation by that qualifying BTM DES facility or qualifying BTM DES aggregation.
"(2) Requirement.--The manner in which the data described in paragraph (1) is used to adjust the retail bill of a customer, including any adjustment to account for energy exported or withdrawn, shall be determined by the State regulatory authority having jurisdiction over retail rates.
"(d) Prohibition on Interference.--
"(1) In general.--No distribution utility shall use its control over the distribution system, metering, customer data, or retail sales to prevent any behind-the-meter resource eligible to participate in a wholesale market subject to the jurisdiction of the Commission from participating in such wholesale market (including by denying, diminishing, or preventing reasonable access by the applicable Transmission Organization, aggregator, or system operator to customer data).
"(2) Data parity.--If a distribution utility bids resources into the wholesale market, the distribution utility shall provide data parity between itself and aggregators to ensure that access to necessary customer data does not provide the distribution utility a competitive advantage over third-party aggregators.
"(e) Commission Enforcement.--
"(1) In general.--The Commission shall have authority to enforce the provisions of this section, and any person may file with the Commission a complaint alleging a violation of this section.
"(2) Direct effects.--The failure or refusal of a distribution utility to provide to a Transmission Organization, aggregator, or system operator access to customer data, including metering data collected by advanced metering infrastructure, necessary to facilitate the participation of BTM DES facilities shall be considered as having a direct effect on wholesale rates.
"(3) Requirement.--The Commission shall act on the merits of any complaint filed under paragraph (1) not later than 180 days after the date on which the complaint is filed.
"(f) Applicability to Public Power and Certain Cooperatives.--Except to the extent that compliance is required under State law, the requirements of subsections (b), (c), and (d) shall be voluntary with respect to distribution utilities that are entities described in section 201(f).".
(e) Establishment of Program to Facilitate Voluntary Streamlined Process for Local Permitting of Qualifying Distributed Energy Systems.--
(1) Definitions.--In this subsection:
(A) Authority having jurisdiction.--The term "authority having jurisdiction" means any State, county, local, or Tribal office or official with jurisdiction--
(i) to issue permits relating to qualifying distributed energy systems;
(ii) to conduct inspections to enforce the requirements of a relevant code or standard relating to qualifying distributed energy systems; or
(iii) to approve the installation of, or the equipment and materials used in the installation of, qualifying distributed energy systems.
(B) Qualifying distributed energy system.--The term "qualifying distributed energy system" means any equipment or materials installed in, on, or near a building or premises to support onsite or local energy use, including equipment or materials, the primary function of which is--
(i) to generate electricity from distributed renewable energy sources, including solar photovoltaic systems or similar solar energy technologies;
(ii) to store and discharge electricity from batteries with a capacity of at least 2 kilowatt hours;
(iii) to charge a plug-in electric drive vehicle at a power rate of at least 2 kilowatts; or
(iv) to refuel a hydrogen fuel cell electric vehicle.
(C) Secretary.--The term "Secretary" means the Secretary of Energy.
(2) Program.--Not later than 180 days after the date of enactment of this Act, the Secretary, in consultation with trade associations and other entities representing distributed energy system installers, organizations representing State, local, and Tribal governments engaged in permitting, and other interested stakeholders, shall carry out a program to further develop, expand, and support the adoption of a voluntary streamlined permitting and inspection process for authorities having jurisdiction to use for the permitting of qualifying distributed energy systems.
(3) Activities of the program.--In carrying out the program established under paragraph (2), the Secretary shall--
(A) further develop and expand an exemplary streamlined permitting process that includes an online permitting platform--
(i) for expediting, standardizing, and streamlining permitting; and
(ii) that authorities having jurisdiction may voluntarily use to receive, review, and approve permit applications relating to qualifying distributed energy systems;
(B) establish targets for the adoption of a streamlined, expedited permitting process by authorities having jurisdiction;
(C) provide technical assistance and training directly or indirectly to authorities having jurisdiction on using and adopting the exemplary streamlined permitting process described in subparagraph (A), including the adoption of any necessary building codes;
(D) develop a voluntary inspection protocol and related tools to expedite, standardize, and streamline the inspection of qualifying distributed energy systems, including--
(i) by investigating the potential for using remote inspections;
(ii) by investigating the potential for sample-based inspection for distributed energy system installers with a demonstrated track record of high-quality work; and
(iii) by investigating opportunities to integrate the voluntary inspection protocol into the online permitting platform described in subparagraph (A) and the platforms of government software providers; and
(E) take any other action to expedite, standardize, streamline, or improve the process for permitting, inspecting, or interconnecting qualifying distributed energy systems.
(4) Support services.--The Secretary shall--
(A) support the provision of technical assistance to authorities having jurisdiction, any administrator of the online permitting platform described in paragraph (3)(A), government software providers, and any other entity determined appropriate by the Secretary in carrying out the activities described in paragraph (3); and
(B) provide such financial assistance as the Secretary determines appropriate from any funds appropriated to carry out this subsection.
(5) Authority having jurisdiction certification program.--
(A) In general.--The Secretary may certify authorities having jurisdiction that implement the exemplary streamlined permitting process described in paragraph (3)(A).
(B) Process.--The Secretary may confer a certification under subparagraph (A) through existing programs within the Department of Energy.
(C) Prizes.--The Secretary may award prizes to authorities having jurisdiction, using funds appropriated to the Secretary to carry out this subsection, to encourage authorities having jurisdiction to adopt the exemplary streamlined permitting process or the voluntary inspection protocol established under subparagraphs (A) and (D) of paragraph (3), respectively.
(6) Authorization of appropriations.--There is authorized to be appropriated to the Secretary to carry out this subsection $20,000,000 for each of fiscal years 2026 through 2031.
______
SA 7017. Mr. WELCH submitted an amendment intended to be proposed to amendment SA 6883 proposed by Mr. Thune (for Mrs. Capito (for herself, Mr. Lee, Mr. Whitehouse, and Mr. Heinrich)) to the bill H.R. 2347, to amend the Internal Revenue Code of 1986 to exclude from gross income any damages, other than punitive damages, received on account of any sexual acts or sexual contact; which was ordered to lie on the table; as follows:
Text printed in the Record (10,192 characters)
At the appropriate place in title I of division B, insert the following:
SEC. 21__. ENSURING COMMUNITY BENEFITS.
(a) Definitions.--In this section:
(1) Covered loan.--The term "covered loan" means any of the following issued after the date of enactment of this Act:
(A) A loan issued under section 40106(e)(1)(B) of the Infrastructure Investment and Jobs Act (42 U.S.C. 18713(e)(1)(B)).
(B) A loan made for an eligible project described in paragraph (2)(B) under the Transmission Infrastructure Program of the Western Area Power Administration.
(C) Any other loan made under a Department of Energy loan program identified in the report required under subsection (f)(1) with respect to electric power transmission lines that are capable of transmitting 999 megawatts or more.
(2) Eligible project.--The term "eligible project" means--
(A) an eligible project (as defined in section 40106(a) of the Infrastructure Investment and Jobs Act (42 U.S.C. 18713(a))) that is carried out using a covered loan described in paragraph (1)(A);
(B) a project for the purpose of constructing, financing, facilitating, planning, operating, or maintaining, or studying the construction of, new or upgraded electric power transmission lines and related facilities with at least 1 terminus within the service territory of the Western Area Power Administration that is carried out using a covered loan described in paragraph (1)(B); or
(C) a project with respect to electric power transmission lines capable of transmitting 999 megawatts or more that is carried out using a covered loan described in paragraph (1)(C).
(3) Fund.--The term "Fund" means the Community Economic Development Transmission Fund established under subsection (b).
(4) Host community.--The term "host community" means--
(A) a local government, such as a municipality, town, or county, with jurisdiction over any land on which an eligible project is or will be carried out; or
(B) an Indian Tribe with jurisdiction over any land on which an eligible project is or will be carried out.
(5) Indian tribe.--The term "Indian Tribe" has the meaning given the term in section 4 of the Indian Self-Determination and Education Assistance Act (25 U.S.C. 5304).
(6) Secretary.--The term "Secretary" means the Secretary of Energy.
(b) Establishment.--There is established in the Treasury a fund, to be known as the "Community Economic Development Transmission Fund"--
(1) consisting of such amounts as may be deposited in the Fund pursuant to subsection (c); and
(2) that shall be managed and administered by the Secretary to make payments, in accordance with this section, to host communities.
(c) Deposits in the Fund.--
(1) In general.--Notwithstanding any other provision of law, a portion, determined in accordance with paragraph (2), of the interest charged and collected with respect to a covered loan each fiscal year shall be deposited in the Fund to carry out the provisions of this Act.
(2) Determination of portion.--The Secretary, in consultation with the Secretary of the Treasury, shall determine the portion of interest charged and collected each fiscal year that shall be deposited in the Fund under this subsection.
(d) Expenditures From the Fund.--
(1) Availability of amounts.--Amounts in the Fund shall be available, as provided in appropriation Acts, for making payments as described in subsection (b)(2).
(2) Payments.--
(A) In general.--The Secretary shall make a payment to a host community under this section not later than 18 months after construction of the applicable eligible project commences.
(B) Single sum.--For any 1 eligible project, the Secretary may make not more than 1 payment under this section to each host community eligible to receive a payment relating to that eligible project.
(3) Eligibility.--A host community shall be eligible to receive a payment under this section if the host community--
(A) submits a request to the Secretary not later than 1 year after the host community receives notice under paragraph (4); and
(B) certifies to the Secretary that the funds will be used for an eligible purpose described in subsection (e).
(4) Notice.--The Secretary shall provide host communities notice of the availability of payments under this section as part of the Federal siting and permitting processes for the applicable eligible project.
(5) Payment amount.--In determining the amount of a payment to a host community under this section, the Secretary shall--
(A) develop and use a formula for disbursement of funds that, to the extent practicable, ensures the long-term solvency of the Fund; and
(B) in developing that formula--
(i) take into account input from host communities and stakeholder groups regarding the impacts of eligible projects on host communities; and
(ii) include a small-population community minimum as part of the formula.
(6) Payments in lieu of taxes.--Any amount received by a host community from a payment made under this section shall be in addition to any payment in lieu of taxes received by the host community under chapter 69 of title 31, United States Code.
(e) Eligible Use of Funds.--
(1) Community support.--A host community may use up to 80 percent of the amounts received by that host community from a payment under this section to develop, deliver, or support--
(A) services, projects, or programs that--
(i) improve existing infrastructure or implement essential public services, including services, projects, or programs relating to--
(I) public schools; (II) public libraries; (III) public hospitals; (IV) roads, bridges, or public transportation; (V) community centers or parks; (VI) firefighting or search and rescue services; or (VII) law enforcement;
(ii) provide or expand access to--
(I) broadband telecommunications services at local community anchor institutions (as defined in section 60302 of the Digital Equity Act of 2021 (47 U.S.C. 1721));
(II) technology or connectivity needed for students to use a digital learning tool at or outside of a local school campus; or
(III) farmers markets or other agricultural support;
(iii) support local agricultural processing or distribution infrastructure;
(iv) support workforce training programs for technical training, skill mastery, or business opportunities across the spectrum of careers in renewable energy, with emphasis on historically underrepresented communities in the renewable energy workforce; or
(v) address public health by increasing outdoor recreation opportunities, including construction of new parks, for people of all backgrounds and abilities; or
(B) other, similar services, projects, or programs.
(2) Conservation, stewardship, and recreation.--A host community shall use at least 20 percent of the amounts received by that host community from a payment under this section for conservation, stewardship, or recreation purposes, including--
(A) restoring or protecting--
(i) fish or wildlife habitat;
(ii) fish or wildlife corridors; or
(iii) wetlands, streams, rivers, or other natural water bodies in areas affected by transmission development;
(B) preserving or improving recreational access to public land or water through an easement, right-of-way, or other instrument from willing landowners for the purpose of enhancing public access to existing Federal land or water that is inaccessible or restricted;
(C) developing new or renovating existing outdoor recreation facilities that provide outdoor recreation opportunities to the public;
(D) creating or significantly enhancing access to park or recreational opportunities in a neighborhood or community;
(E) engaging or empowering underserved communities or youth;
(F) facilitating public-private partnerships to enhance public outdoor recreational access, infrastructure improvements, or conservation efforts;
(G) for natural climate solutions, including programs that--
(i) accommodate biochar or other nature-based opportunities for carbon sequestration;
(ii) support wildfire resilience to ensure healthy and resilient forests or grasslands;
(iii) promote the planting, growing, or restoring of trees or forests;
(iv) support resilience against natural disasters to ensure healthy and resilient communities;
(v) empower farmers in the United States to incorporate conservation or climate co-benefits in their agricultural practices; or
(vi) support or implement traditional ecological knowledge; or
(H) other, similar services, projects, or programs.
(f) Reports.--
(1) Coverage.--Not later than 90 days after the date of enactment of this Act, the Secretary shall submit to the Committee on Energy and Natural Resources of the Senate and the Committee on Energy and Commerce of the House of Representatives a report detailing the loan programs within the Department of Energy that fund electric power transmission lines and related infrastructure that are capable of transmitting 999 megawatts or more.
(2) Annual report.--
(A) In general.--Not later than 60 days after the end of each fiscal year, the Secretary shall submit to the Committee on Energy and Natural Resources of the Senate and the Committee on Energy and Commerce of the House of Representatives a report on the operation of the Fund during that fiscal year.
(B) Report requirements.--Each report submitted under subparagraph (A) shall include--
(i) a statement of--
(I) the amounts deposited in the Fund during the applicable fiscal year; and
(II) the balance remaining in the Fund at the end of that fiscal year; and
(ii) a list of--
(I) host communities that received amounts made available from the Fund during that fiscal year;
(II) the associated eligible projects carried out in those host communities; and
(III) the amount that each of those host communities received.
(g) Savings Provision.--Nothing in this section, including the receipt of amounts made available from the Fund--
(1) precludes a host community from entering into a community benefit agreement with an owner of transmission infrastructure; or
(2) otherwise affects the authority of a host community or an owner of transmission infrastructure with respect to any community benefit agreement.
______
SA 7018. Mr. WELCH submitted an amendment intended to be proposed to amendment SA 6883 proposed by Mr. Thune (for Mrs. Capito (for herself, Mr. Lee, Mr. Whitehouse, and Mr. Heinrich)) to the bill H.R. 2347, to amend the Internal Revenue Code of 1986 to exclude from gross income any damages, other than punitive damages, received on account of any sexual acts or sexual contact; which was ordered to lie on the table; as follows:
Text printed in the Record (7,864 characters)
At the appropriate place in title I of division B, insert the following:
SEC. 21__. SHARED UTILITY REWARDS FOR GRID EFFICIENCY.
(a) Definitions.--In this section:
(1) Advanced conductor.--The term "advanced conductor" means an electric transmission conductor that, relative to a conductor being replaced on a given transmission or distribution line, is designed to substantially improve electrical or mechanical performance through the achievement of at least 1 of the following criteria, as determined by the Commission:
(A) A substantial increase in current-carrying capacity under normal operating conditions.
(B) A substantial reduction in electrical resistance or line losses under normal operating conditions.
(C) Operation at materially higher continuous allowable operating temperatures.
(D) A reduction in thermal sag or mechanical constraints that enables increased use of a transmission segment or facility.
(2) Appropriate congressional committees.--The term "appropriate congressional committees" means--
(A) the Committee on Energy and Commerce of the House of Representatives; and
(B) the Committee on Energy and Natural Resources of the Senate.
(3) Bulk-power system; electric utility; independent system operator; regional transmission organization; state regulatory authority; transmitting utility.--The terms "bulk-power system", "electric utility", "Independent System Operator", "Regional Transmission Organization", "State regulatory authority", and "transmitting utility" have the meanings given those terms in section 3 of the Federal Power Act (16 U.S.C. 796).
(4) Commission.--The term "Commission" means the Federal Energy Regulatory Commission.
(5) Covered action.--
(A) In general.--The term "covered action" means an action that would generate cost savings for ratepayers.
(B) Exclusion.--The term "covered action" does not include the construction of a new facility or the complete reconstruction of an existing facility.
(6) Covered electric utility.--The term "covered electric utility" means an electric utility not subject to the jurisdiction of the Commission for ratemaking purposes under part II of the Federal Power Act (16 U.S.C. 824 et seq.).
(7) Covered transmission action.--The term "covered transmission action" means a covered action to improve the efficiency, capacity, reliability, or resilience of 1 or more transmission facilities or transmission segments, including through--
(A) the replacement of a conductor on a transmission line within such a facility or segment with an advanced conductor; or
(B) the deployment of a grid-enhancing technology.
(8) Covered transmitting utility.--The term "covered transmitting utility" means a transmitting utility subject to the jurisdiction of the Commission for ratemaking purposes under part II of the Federal Power Act (16 U.S.C. 824 et seq.).
(9) Covered utility action.--The term "covered utility action" means a covered action taken by an electric utility--
(A) to improve the efficiency of the generation, transmission, or distribution of electric energy, including by reducing the proportion of electrical energy lost during such generation, transmission, or distribution (including through the deployment of energy storage systems or other technologies); or
(B) to reduce the consumption of, or peak demand for, electric energy, including through--
(i) a technological improvement, such as the deployment of high-efficiency appliances, smart thermostats, distributed energy resources, or building retrofits;
(ii) the establishment of a pricing mechanism to encourage customers of the electric utility to reduce such consumption or shift such demand to non-peak hours; or
(iii) any other action or program to incentivize or otherwise produce such a reduction or shift in demand.
(10) Grid-enhancing technology.--The term "grid-enhancing technology" means any hardware or software that--
(A) increases the capacity, efficiency, reliability, resilience, or safety of transmission facilities and transmission technologies; and
(B) is installed, in addition to transmission facilities and transmission technologies, for the purpose of--
(i) providing operators of such facilities and technologies increased situational awareness and control over the electric grid;
(ii) improving the efficiency of such facilities and technologies;
(iii) increasing the transfer capacity of such facilities and technologies; or
(iv) otherwise enabling the increased use, or more efficient of use, of such facilities and technologies under normal operating conditions.
(11) Qualifying action.--The term "qualifying action" means a covered transmission action achieved through the reduction of the quantity of electrical energy that enters a transmission segment but does not exit the transmission segment, as measured over a prescribed period of time (commonly referred to as "transmission physical loss").
(12) Secretary.--The term "Secretary" means the Secretary of Energy.
(13) Transmission segment.--The term "transmission segment" means a functionally distinct portion of an interconnected transmission system (such as a single transmission line or multiple transmission lines within a prescribed zone, such as between prescribed substations), for which the quantity of electrical energy transmitted and the quantity of electrical energy lost during such transmission may be independently measured, as determined by the Commission.
(b) Federal Power Act Amendments.--Section 219 of the Federal Power Act (16 U.S.C. 824s) is amended--
(1) in subsection (a)--
(A) by striking "Not later than 1 year after the date of enactment of this section, the Commission shall establish, by rule," and inserting "The Commission shall issue such rules as may be necessary to establish"; and
(B) by inserting ", improving efficiency," after "ensuring reliability";
(2) in subsection (b)--
(A) in the matter preceding paragraph (1), by striking "The rule shall" and inserting "The rules issued under this section shall";
(B) in paragraph (1), by inserting ", and operational improvements for," after "capital investment in";
(C) in paragraph (2)--
(i) by inserting "or other incentive mechanism" after "return on equity"; and
(ii) by inserting "or incentivizes improvements that increase the efficiency of the transmission of electric energy and reduce costs for consumers" after "(including related transmission technologies)";
(D) in paragraph (3), by inserting ", including performance-based measures," after "other measures"; and
(E) in paragraph (4) (as amended by section 2101(h))--
(i) in subparagraph (B), by striking "and" after the semicolon at the end;
(ii) in subparagraph (C), by striking the period at the end and inserting "; and"; and
(iii) by adding at the end the following:
"(D) amounts determined pursuant to shared savings frameworks or other incentive mechanisms prescribed in such rules."; and
(3) in subsection (c), by striking "In the rule" and inserting "In a rule".
(c) Rulemaking on Shared Savings Framework for Transmitting Utilities Subject to Commission Jurisdiction.--
(1) Definitions.--In this subsection:
(A) Shared savings framework.--The term "shared savings framework" means a framework under which a covered transmitting utility may recover a portion of verified cost savings attributable to a qualifying action of the transmitting utility as an incentive.
(B) Similarly situated.--The term "similarly situated", with respect to transmission segments, means transmission segments that the Commission determines share comparable characteristics, such as voltage class, geography, load profile, or historical performance.
(2) Rule required.--Not later than 1 year after the date of enactment of this Act, the Commission shall issue a final rule under section 219(b)(3) of the Federal Power Act (16 U.S.C.
Text printed in the Record (9,195 characters)
824s(b)(3)) that establishes shared savings frameworks.
(3) Methodologies.--The Commission shall develop and include in the rule under paragraph (2) standardized methodologies, applicable across similarly situated transmission segments, as follows:
(A) Baseline performance methodologies.--Methodologies, developed in consultation with the Secretary, for covered transmitting utilities to determine the annual baseline performance of transmission facilities or transmission segments absent qualifying actions--
(i) by measuring the baseline performance of such a transmission facility or transmission segment--
(I) through the actual quantity of electrical energy entering and leaving such facility or segment (commonly referred to as "direct metering"); or
(II) if the method under subclause (I) is not feasible, through an estimation of such quantity consistent with modeling methodologies prescribed by the Commission; and
(ii) by normalizing data to ensure such baseline performance accounts for variability in exogenous factors determined by the Commission, such as variability in--
(I) weather;
(II) demand over time;
(III) upgrades, interconnections, or operational changes made by other utilities, Independent System Operators or Regional Transmission Organizations, or other entities determined relevant by the Commission; or
(IV) other conditions affecting demand or generation.
(B) Methodologies relating to cost savings.--Methodologies for covered transmitting utilities to estimate and calculate, and for independent evaluators to verify, the cost savings attributable to qualifying actions under the shared savings framework, taking into account--
(i) the baseline performance of any transmission facility or transmission segment with respect to which a qualifying action is conducted; and
(ii) price proxies, determined according to a methodology prescribed by the Commission, for the value of electric energy transmitted (which may include, for a region
managed by an Independent System Operator or Regional Transmission Organization, the locational marginal price corresponding to the location on the electric grid where an injection or withdrawal of power is modeled (commonly referred to as a "pricing node")).
(C) Methodologies relating to recoverable percentage and rate recovery timeline.--
(i) In general.--Methodologies for covered transmitting utilities to determine, taking into account the factors described in clause (ii), the following:
(I) The total percentage of cost savings attributable to a qualifying action that such a utility may recover as an incentive under the shared savings framework, which may not be less than 10 percent or greater than 60 percent of such total attributable cost savings (referred to in this subsection as the "recoverable percentage" of such savings).
(II) The period of time during which such a utility may recover amounts as an incentive for such an action, which may not be shorter than a 2-year period or longer than a 5-year period (referred to in this subsection as the "rate recovery timeline" for such action).
(ii) Factors.--The factors described in this clause are the following:
(I) The extent of financial or operational risk to be assumed by a covered transmitting utility in conducting a qualifying action.
(II) The baseline performance for transmission facilities or transmission segments with respect to which such action is to be conducted.
(III) The replicability or demonstration value of such action.
(IV) The duration of cost savings predicted to result from such action and whether such cost savings will remain consistent over such duration.
(V) The extent to which such action is expected to result in additional benefits, such as improvements to the resilience or the reliable operation of the bulk-power system, reductions to transmission congestion, or reductions to greenhouse gas emissions.
(VI) Such other factors as the Commission may determine relevant to ensure the incentive is performance-based, transparent, and cost-effective.
(4) Initial filing required.--To be considered for an incentive under the shared savings framework for the conduct of a qualifying action, a covered transmitting utility shall submit to the Commission an initial filing, the contents of which shall be verified by an independent evaluator determined appropriate by the Commission, that includes the following:
(A) An identification of the baseline performance of any transmission facility or transmission segment with respect to which such action is to be conducted for the 1-year period preceding the date on which such conduct is to be commenced, determined by such utility pursuant to an applicable methodology under paragraph (3)(A) (including the data underlying such calculation).
(B) A description of such action, including an analysis of improvements expected to result from such action.
(C) The rate recovery timeline for such action and the recoverable percentage of cost savings attributable to such action, determined pursuant to an applicable methodology under paragraph (3)(C).
(D) An estimate, developed pursuant to an applicable methodology under paragraph (3)(B), of the cost savings to result from such action for--
(i) the 1-year period beginning on the date on which the conduct of such action commences; and
(ii) the duration of the rate recovery timeline for such action.
(E) A claim for 50 percent of the recoverable percentage of cost savings estimated under subparagraph (D)(i).
(F) An agreement by such utility to file with the Commission the annual reports required under paragraph (5), the contents of which shall be verified by an independent evaluator determined appropriate by the Commission.
(5) Annual reporting required.--Beginning 1 year after the date on which a covered transmitting utility submits an initial filing for a qualifying action under paragraph (4), and on an annual basis thereafter until the end of the rate recovery timeline for such action determined under subparagraph (C) of that paragraph or until such action no longer results in cost savings, whichever occurs first, such utility shall file with the Commission a report containing, with respect to the qualifying action of such utility, the following:
(A) Data on the performance during the preceding year of any transmission facility or transmission segment with respect to which such action was conducted, and a comparison of such performance to the baseline performance of that transmission facility or transmission segment determined pursuant to an applicable methodology under paragraph (3)(A) for such year.
(B) The actual cost savings attributable to the qualifying action for the preceding year, calculated pursuant to an applicable methodology under paragraph (3)(B).
(C) If such utility expects cost savings to result from the qualifying action during the following year, an estimate, developed pursuant to an applicable methodology under paragraph (3)(B) of the cost savings for such following year.
(D) A claim for the following:
(i) An amount that is the recoverable percentage of the actual cost savings for the preceding year calculated under subparagraph (B) minus any amount previously recovered based on an estimate of cost savings for such year under subparagraph (A) or (B)(ii) of paragraph (6), as applicable.
(ii) If the report includes an estimate of cost savings for the following year under subparagraph (C), an amount that is 50 percent of the recoverable percentage of such estimated cost savings.
(E) If such utility finds that the total amount recovered for a year under paragraph (6) exceeds the amount equal to the total recoverable percentage of the actual cost savings for that year under subparagraph (B), an identification of the excess amount.
(6) Recovery mechanism.--
(A) Rate adjustment based on initial filing.--Not later than 60 days after receiving an initial filing of a covered transmitting utility under paragraph (4), the Commission shall provide to such utility a rate adjustment under which such utility may recover the amount claimed under paragraph (4)(E).
(B) Rate adjustment based on annual reports.--Not later than 60 days after receiving an annual report of a covered transmitting utility under paragraph (5), the Commission shall provide to such utility a rate adjustment under which--
(i) subject to subparagraph (C), such utility may recover the amount claimed under paragraph (5)(D)(i); and
(ii) if the report included a claim under paragraph (5)(D)(ii), such utility may recover the amount so claimed.
(C) Reconciliation.--If a utility identifies an excess amount under paragraph (5)(E), or the Commission determines the information reported for that year under paragraph (5) is insufficient for purposes of this subsection, the Commission shall credit the difference to ratepayers through a rate adjustment.
(7) Sense of congress regarding additional rulemakings.--It is the sense of Congress that--
(A) following the issuance of the rule under paragraph (2), the Commission should revise such rule, or issue additional rules under the authority of section 219(b)(3) of the Federal Power Act (16 U.S.C.
Text printed in the Record (11,964 characters)
824s(b)(3)) to expand the shared savings framework to additional categories of measurable, demonstrable, and verifiable covered transmission actions;
(B) any such rule should include a version of the methodologies developed under paragraph (3) adapted for such additional categories; and
(C) any such rule should take into account the findings of the most recently conducted study under subsection (f).
(d) Guidance for Electric Utilities Not Subject to Federal Energy Regulatory Commission Jurisdiction.--
(1) In general.--Not later than 2 years after the date of enactment of this Act, the Secretary, in coordination with the Commission and State regulatory authorities, shall develop and publish on a publicly available website of the Department of Energy guidance to support State regulatory authorities in establishing frameworks under which covered electric utilities may recover a portion of verified cost savings attributable to a covered utility action as an incentive.
(2) Minimum elements.--The guidance under paragraph (1) shall include--
(A) guidance, developed in accordance with paragraph (3), for determining the baseline performance of a covered electric utility absent a covered utility action;
(B) guidance, developed in accordance with paragraph (4), for determining the cost savings attributable to a covered utility action;
(C) guidance for the measurement and verification of a covered utility action, and any cost savings attributable to such action, by an independent evaluator determined appropriate by the State regulatory authority concerned;
(D) guidance on potential mechanisms by which covered electric utilities may recover a portion of the verified cost savings attributable to a covered utility action, including through the provision of rate adjustments by State regulatory authorities; and
(E) such other elements as the Secretary determines appropriate to ensure the framework specified in paragraph (1) is transparent, performance-based, cost-effective, and consistent with State ratemaking practices.
(3) Methodology for determining baseline performance.--
(A) In general.--In developing the guidance under paragraph (2)(A), the Secretary, in coordination with the Commission, shall--
(i) consult with State regulatory authorities, Independent System Operators, Regional Transmission Organizations, and independent evaluators determined appropriate by the Secretary regarding such guidance;
(ii) include in such guidance technical guidance for normalizing data to ensure the baseline performance of a covered electric utility accounts for variability in exogenous factors, such as variability in--
(I) weather;
(II) demand over time;
(III) upgrades, interconnections, or operational changes made by other utilities, Independent System Operators or Regional Transmission Organizations, or other entities determined relevant by the Commission; or
(IV) other conditions affecting demand or generation, as determined by the Secretary; and
(iii) ensure such guidance supports consistent treatment across covered electric
utilities within each category described in paragraph (5).
(B) Support from national laboratories.--The National Laboratories shall provide such technical support as the Secretary determines necessary to carry out this paragraph.
(4) Guidance on determining cost savings.--In developing the guidance under paragraph (2)(B), the Secretary shall--
(A) include in such guidance--
(i) principles to ensure that cost savings attributable to a covered utility action are calculated in a manner that takes into account price proxies for the value of electric energy and the baseline performance of the covered electric utility; and
(ii) tools, technical support, and reference data to assist State regulatory authorities in applying the principles specified in clause (i); and
(B) ensure such guidance supports consistent treatment across covered electric utilities within each category described in paragraph (5).
(5) Applicability to utility market structures.--In carrying out paragraph (1), the Secretary shall develop separate guidance for each category of covered electric utilities as follows:
(A) Covered electric utilities (commonly referred to as "vertically integrated utilities") that--
(i) own and operate generation, transmission, and distribution facilities; and
(ii) directly provide retail electric service to end-use customers.
(B) Covered electric utilities that own or operate transmission infrastructure but not distribution or generation infrastructure.
(C) Covered electric utilities that own or operate distribution infrastructure but not transmission or generation infrastructure.
(D) Covered electric utilities that own or operate distribution and transmission infrastructure but not generation infrastructure.
(6) Revisions.--On the publication of each report under subsection (f), the Secretary shall determine whether to revise the guidance under paragraph (1), taking into account the contents of such report and the recommendations included therein.
(e) Grant Program for State Regulatory Authorities.--
(1) Establishment.--Not later than 2 years after the date of enactment of this Act, the Secretary shall establish a program under which the Secretary may award grants to State regulatory authorities to support the development, implementation, and oversight by such State regulatory authorities of frameworks under which covered electric utilities may recover a portion of verified cost savings attributable to a covered utility action as an incentive (referred to in this subsection as the "grant program").
(2) Authorized uses of funds.--Amounts awarded under the grant program may only be used to conduct the following activities:
(A) The development of a framework referred to in paragraph (1), or revision of an existing such framework, such that the framework is consistent with the guidance developed under subsection (d), including the following:
(i) The development, including the design or modeling, of methodologies consistent with the methodologies set forth under such guidance.
(ii) The development of data systems or other tools necessary for the development of the framework.
(iii) The issuance or revision of regulations necessary for the development of the framework.
(iv) The engagement with stakeholders with respect to the development of the framework.
(B) The implementation or oversight of a framework consistent with such guidance.
(3) Prohibited use of funds.--No amounts awarded under the grant program may be used to pay a covered electric utility.
(4) Grant recipient reporting requirement.--
(A) In general.--As a condition of receiving amounts under the grant program, a State regulatory authority shall agree to submit to the Secretary, on an annual basis for the duration of the period in which such State regulatory authority expends such amounts, a report describing the activities carried out using such amounts.
(B) Effect of noncompliance.--If a grant recipient fails to submit a report required under subparagraph (A), such recipient shall be ineligible for additional awards under this section until the report is submitted.
(5) Administration of program.--
(A) Technical support; public registry.--In carrying out the grant program, the Secretary shall--
(i) provide to grant recipients technical assistance in support of activities conducted using amounts awarded under the grant program; and
(ii) maintain a publicly accessible registry of the activities so conducted.
(B) Reporting by secretary.--Not later than 2 years after the date of enactment of this Act, and biennially thereafter for the duration of the grant program, the Secretary shall submit to the appropriate congressional committees a report containing--
(i) a summary of the activities conducted using amounts awarded under the grant program;
(ii) an assessment of the effectiveness of any framework implemented using such amounts; and
(iii) an identification of any barrier to the development, implementation, or oversight of a framework consistent with the guidance developed under subsection (d) and recommendations for addressing such barrier, as applicable.
(C) Allocation of funds.--Of the amounts authorized to be appropriated or otherwise made available to the Secretary to carry out the grant program--
(i) not more than 70 percent may be awarded for the conduct of activities under paragraph (2)(A);
(ii) not less than 30 percent may be awarded for the conduct of activities under paragraph (2)(B); and
(iii) not more than 5 percent may be obligated or expended for Federal administrative expenses.
(f) Studies on Effects of Certain Rate Treatments and Alternative Frameworks.--
(1) Studies required.--Not later than 3 years after the date of enactment of this Act, and every 5 years thereafter, the Secretary, in consultation with the Commission, shall--
(A) conduct a study on--
(i) inefficiencies in the electric power sector incentivized by existing rate treatments for the transmission of electric energy and any economic, environmental, or societal effect of such inefficiencies, including with respect to the customers of electric utilities, the reliable operation of the bulk-power system, and the deployment of cost-effective grid-enhancing technologies; and
(ii) alternative frameworks for incentive-based, including performance-based, rate treatments for such transmission, such as the alternative frameworks described in paragraph (2); and
(B) publish on a publicly available website of the Department of Energy, and submit to the appropriate congressional committees, a report that includes--
(i) a detailed description of the findings of such study; and
(ii) recommendations of the Secretary to align rate treatments for the transmission of electric energy with the goals of lowering costs for the customers of electric utilities, enhancing the reliable operation of the bulk-power system, reducing transmission congestion and other inefficiencies in the transmission or delivery of electric energy, and encouraging the deployment of cost-effective grid-enhancing technologies.
(2) Examples of alternative frameworks.--The alternative frameworks described in this paragraph are the following:
(A) Shared savings frameworks.
(B) Revenue decoupling models, under which authorized revenues of utilities are separated from volumetric sales of electricity to reduce disincentives for energy efficiency and programs to reduce the consumption of, or peak demand for, electric energy.
(C) Return on equity adjustments, under which authorized utility returns are increased or decreased based on measurable factors such as risk profile, performance outcomes, or efficiency improvements.
(D) Multi-year rate plans, under which revenue requirements and performance expectations for utilities are established for a fixed multi-year period rather than through single-year rate cases.
(E) Earnings sharing mechanisms, under which earnings of utilities falling outside an authorized range as compared to the return on equity are shared between shareholders and ratepayers.
(F) Total expenditure models, under which capital and operating expenditures of utilities are treated on an equivalent basis to reduce bias toward capital investment.
(G) Performance scorecards, under which utilities are evaluated against transparent outcome-based metrics such as reliability, affordability, equity, or the reduction of emissions, with results informing regulatory decisions or incentive adjustments.
(3) Sources.--The Secretary shall ensure that each study under paragraph (1) is informed by--
(A) reports filed with the Commission pursuant to subsections (c) and (e) and section 304 of the Federal Power Act (16 U.S.C. 825c);
(B) relevant reports issued by the National Laboratories; and
(C) such other studies, reports, and other data sources as the Secretary may determine appropriate.
______
SA 7019. Ms. MURKOWSKI (for herself and Mr. Schatz) submitted an amendment intended to be proposed to amendment SA 6999 submitted by Ms. Murkowski (for herself, Mr. Schatz, Ms. Cantwell, Mr. Gallego, Mr. Lujan, and Mr. Hickenlooper) and intended to be proposed to the amendment SA 6883 proposed by Mr. Thune (for Mrs. Capito (for herself, Mr. Lee, Mr. Whitehouse, and Mr. Heinrich)) to the bill H.R. 2347, to amend the Internal Revenue Code of 1986 to exclude from gross income any damages, other than punitive damages, received on account of any sexual acts or sexual contact; which was ordered to lie on the table; as follows:
Text printed in the Record (1,630 characters)
On page 5 of the amendment, strike lines 3 and 4 and insert the following:
zation.";
(4) in subsection (a)(7) (as added by paragraph (3))--
(A) in subparagraph (B)(ii), by striking "that is not for the primary purpose of historic preservation, subject to the condition
that this clause shall not apply to a project that receives more than $10,000,000 of financial assistance from the Department of Transportation" and inserting "with respect to which a Federal agency does not exercise predominant control and responsibility over the subsequent use of such financial assistance or any adverse effect of the project, activity, or program on a historic property"; and
(B) by adding at the end the following:
"(C) Rule of construction with respect to federal financial assistance.--
"(i) Transportation projects.--For purposes of clause (ii) of subparagraph (B), the Department of Transportation shall be considered to have predominant control and responsibility over the subsequent use of financial assistance described in that clause for any project, activity, or program that receives more than $10,000,000 of financial assistance from the Department of Transportation.
"(ii) Other federally assisted projects.--Nothing in clause (i) precludes a determination that a Federal agency exercises predominant control and responsibility over the subsequent use of financial assistance described in subparagraph (B)(ii) with respect to a project, activity, or program that receives financial assistance from any other Federal agency, without regard to the amount of such assistance."; and
(5) by adding at the end the following:
SA 7020. Mr. SCHATZ (for himself and Ms. Murkowski) submitted an amendment intended to be proposed to amendment SA 7000 submitted by Ms. Murkowski (for herself, Mr. Schatz, Ms. Cantwell, Mr. Gallego, and Mr. Lujan) and intended to be proposed to the amendment SA 6883 proposed by Mr. Thune (for Mrs. Capito (for herself, Mr. Lee, Mr. Whitehouse, and Mr. Heinrich)) to the bill H.R. 2347, to amend the Internal Revenue Code of 1986 to exclude from gross income any damages, other than punitive damages, received on account of any sexual acts or sexual contact; which was ordered to lie on the table; as follows: On page 1 of the amendment, line 7, strike "$400,000,000" and insert "$300,000,000". At the end of subtitle D of title XXVIII, add the following: ______
SA 7021. Mr. GALLEGO submitted an amendment intended to be proposed by him to the bill S. 4784, to authorize appropriations for fiscal year 2027 for military activities of the Department of Defense, for military construction, and for defense activities of the Department of Energy, to prescribe military personnel strengths for such fiscal year, and for other purposes; which was ordered to lie on the table; as follows:
Text printed in the Record (1,361 characters)
SEC. 2873. PROHIBITION ON SITING OR CONSTRUCTION OF DATA
CENTERS ON MILITARY INSTALLATIONS.
(a) In General.--Subject to subsection (b), the Secretary of Defense and the Secretary of each military department shall not lease land to a non-Federal Government entity or otherwise authorize such an entity to site or construct a new data center on a military installation, including through the use of an enhanced use lease under section 2667 of title 10, United States Code.
(b) Application.--Subsection (a) shall--
(1) apply only to new siting and construction, not to facilities in operation as of the date of the enactment of this Act.
(2) not apply to data centers owned or operated by or for the Department of Defense for national security purposes.
(c) Definitions.--In this section:
(1) Data center.--The term "data center" means a facility, or a group of co-located facilities, the primary purpose of which is to house computer servers, data storage equipment, or networking equipment used to store, process, or transmit electronic data (including for the training or deployment of artificial intelligence or machine learning models), together with associated power, cooling, and security infrastructure.
(2) Military installation.--The term "military installation" has the meaning given that term in section 2801(c) of title 10, United States Code.