Renewable Project Siting and Conservation

Summary#

A-11687 would amend New York’s Environmental Conservation Law and Public Service Law. It would add land-protection limits and local-law requirements for the existing Office of Renewable Energy Siting and Electric Transmission (ORES); its stated goal is to align ORES with the state’s conservation goals. The bill is introduced and has not become law.

  • ORES could not permit a major renewable energy facility that uses, encroaches on, or permanently alters “tier one” lands: forest preserves, state forests, and wildlife management areas.
  • On “tier two” lands, ORES could permit a project only if it meets added conditions. These include transferring land of equivalent or greater ecological value to the state or a qualifying land trust: generally three acres for each affected acre.
  • ORES must also apply relevant uniform and site-specific conditions to tier two projects. The bill requires site-specific conditions when ORES identifies affected land as a priority conservation target.
  • A final permit could issue only if the project complies with applicable laws, including local laws. ORES could not override a local law that prohibits or restricts a facility; a written finding of non-compliance by the host municipality’s governing board would be grounds to deny the permit.
  • The state would have to make annual, uncapped payments to the host municipality for transferred parcels. The minimum would be the parcel’s full assessed value at transfer, adjusted annually, for the permit’s operational life and any renewal.

What it means for you#

  • Renewable energy developers: Projects not yet approved when the law takes effect would face the new land rules. A project affecting tier one land could not be permitted. On tier two land, the developer would have to meet the transfer and other conditions before receiving a permit.
  • Municipalities: Local laws restricting or prohibiting these facilities would have to be respected by ORES. The bill also requires the municipality’s governing board to make a written determination for that determination to bind ORES.
  • Landowners and land trusts: For a tier two project, land of equivalent or greater ecological value would have to be transferred to the state or a qualifying land trust. The bill allows a conservation easement or a fee-simple interest (full ownership).
  • Taxpayers: The state would owe annual payments to host municipalities for transferred parcels. The bill does not create a general tax, fee, or public benefit.
  • General public: The bill does not ban renewable energy projects on all land. It creates a ban on tier one land and conditions on tier two land.

Money#

No cost estimate is provided in the available material.

  • The state must make annual, uncapped payments to host municipalities for transferred parcels, at no less than full assessed value at transfer and adjusted annually.
  • Developers would have to provide the required land transfer for tier two projects. The bill does not estimate the value or cost of those transfers.
  • The bill gives the Department of Environmental Conservation (DEC) a role in setting an ecological-value scoring method by regulation. It does not estimate the cost of that work or of administering the new rules.

What is unclear#

  • The bill does not provide the ecological-value scoring method. DEC would have to set it by regulation.
  • DEC would define how close land must be to tier one land to count as tier two. The bill does not set that distance.
  • The bill does not explain how the state’s annual payment would be calculated or administered when a land trust, rather than the state, receives the easement or land.
  • The definition of a conservation easement calls it voluntary, while the bill makes a land transfer a condition of getting a permit. The relationship between those terms is not explained.
  • The bill does not explain how its new rules would interact with existing permit rules. The parent laws were not supplied, so the current rules and definitions—including which projects count as “major renewable energy facilities”—could not be checked.
  • The bill applies to projects not yet approved when it takes effect, but does not explain how pending applications would be handled.

Case for#

  • The bill appears intended to prevent renewable energy development from permanently changing land the bill treats as especially important for conservation.
  • Requiring more land to be protected for each affected tier two acre could be seen as a way to offset some loss of ecological or agricultural value.
  • Requiring compliance with local laws would give municipalities a direct role in deciding whether a project can be permitted in their jurisdictions.
  • Annual payments to municipalities could compensate them for transferred parcels that are no longer available for other local uses.

Case against#

  • A ban on tier one land and the transfer requirement for tier two land could sharply limit where projects can be permitted. The bill does not estimate the effect on project costs or availability.
  • The three-to-one transfer rule and annual payments could add substantial costs, but the bill provides no estimate or cap on the payments.
  • Key boundaries and judgments—such as ecological value, priority conservation targets, and proximity to tier one land—depend on later decisions or rules that the bill does not spell out.
  • The bill gives local law and a written municipal finding a decisive role in permitting, but does not explain how disagreements about compliance would be resolved.