City approves $3.78M EV charging connections

Summary#

Montréal city council approved a direct-award contract with Hydro-Québec for electrical connections for 200 planned street-side electric-vehicle charging stations in 2027–2028. The maximum cost is $3,782,141.33, taxes included; city staff say the goal is to expand public charging access.

  • Hydro-Québec is the exclusive supplier, so the city awarded the contract without a call for tenders.
  • The work is planned for about 100 sites in 19 boroughs. Hydro-Québec must provide a cost estimate for each site and get the city’s approval before doing that site’s work.
  • Costs of $36,000 or less per site are accepted under the stated rules. Costs of $36,000 or more get further review before acceptance or rejection.
  • The city authorized its infrastructure-project director to sign acceptance letters for the work.
  • This decision covers connections, not the separate purchase or installation contracts for the charging stations.

What it means for you#

  • Residents and charging-station users: The decision supports connections for 200 planned stations. It does not itself install the stations or guarantee when each one will be ready.
  • City residents and taxpayers: The city’s central administration will cover the expense in 2027 and 2028, 50% in each year. The materials do not say how any borrowing costs will be paid.
  • City administration: It must approve each site’s work before Hydro-Québec proceeds there. Higher-cost sites require further review.

Money#

The contract has a maximum cost of $3,782,141.33, taxes included.

  • City staff say $3,453,599.15, net of tax rebates, will be funded through an existing borrowing bylaw for acquiring and installing charging stations.
  • The city will pay after receiving invoices following the stations’ start of operation.
  • No separate estimate of actual final spending is given; the approved amount is a maximum.

What is unclear#

  • The materials do not identify the sites or give the cost estimate for each one.
  • The rules overlap at exactly $36,000: one says costs at or below that amount are accepted, while the other says costs at or above it receive further review.
  • The materials do not explain the detailed criteria for the further review or how the city will assess whether a site’s cost is acceptable.

Case for#

  • City staff say the contract is part of expanding public charging access, with 200 more stations planned across 19 boroughs.
  • The work must be done before the stations can operate, and staff say Hydro-Québec may take up to 18 months to complete connections.
  • Site-by-site estimates and approval give the city a chance to examine higher-cost connections before work proceeds.

Case against#

  • A direct award means there is no call for tenders or competing bids to test the price; the materials identify Hydro-Québec as the exclusive supplier.
  • City staff say sites farther from connection points and more overhead connections are increasing costs. The decision commits up to $3.78 million, but the materials do not show the individual site costs.
  • The review rules for higher-cost sites are not fully explained, and the stated thresholds overlap at exactly $36,000.