City funds two new greenhouses

Summary#

Montréal city council approved a construction contract with L’Archevêque et Rivest ltée for two new greenhouses at the City’s nursery in L’Assomption, in the Lanaudière region. The contract is $1,173,000, and the council also authorized $140,760 for contingencies, bringing the total to $1,313,760, taxes included. City staff say the goal is to replace aging greenhouses and support the City’s tree production.

  • The contract went to the lowest compliant bidder in public call for tenders 26-6028. Three bids were received.
  • The work includes removing the existing greenhouses and building two new ones. The contract lasts 120 days from the order to begin work.
  • The council also required an evaluation of the contractor’s performance after the work.
  • A City project manager and two consultant firms will monitor the work. The tender documents provide for penalties if requirements are not met.

What it means for you#

  • Taxpayers: The City is paying for the work, using funds financed through borrowing bylaw 20-028. The decision does not create a new tax or fee.
  • Boroughs receiving trees: City staff say the nursery currently supplies about 3,300 trees each year to 10 boroughs. The new greenhouses are intended to support production, but the decision does not guarantee a particular increase in tree supply.
  • General public: The decision concerns City facilities and does not directly change residents’ rights or services.

Money#

The authorized total is $1,313,760, taxes included; the net amount after tax rebates is $1,199,637.99.

  • The contractor’s bid is $1,173,000, taxes included. The separate contingency budget is $140,760, taxes included.
  • The City will pay 100% of the expense, with spending planned for 2026 and 2027. The net amount will be financed through borrowing bylaw 20-028.

What is unclear#

  • The decision does not say how much tree production is expected to increase, or when any increase would be achieved.
  • It does not explain how the contingency money may be used or how much, if any, is expected to be spent.
  • The decision gives the contract length but not a specific start date.

Case for#

  • City staff say the existing greenhouses are aging, require repeated repairs and no longer fully support production.
  • The lowest compliant bid was 10.01% below the City’s latest estimate.
  • Replacing the greenhouses could support the nursery’s existing work supplying trees to boroughs.

Case against#

  • The contingency budget is 12% of the contract amount, but the materials do not explain what specific unexpected costs it is meant to cover.
  • Three bids were received; the decision provides no further information about why other firms did not bid or how that affected competition.
  • The decision does not give a forecast of added tree production to weigh against the total cost.