City to rehab sewer pipes with $9M contract

Summary#

Montréal city council approved a contract for sewer-pipe rehabilitation by lining on various streets in the borough of Villeray–Saint-Michel–Parc-Extension. The work covers about 8.1 kilometres of pipes. City staff say the goal is to renew sewer infrastructure while causing less disruption than rebuilding pipes by excavation.

  • The council awarded the contract to Insituform Technologies Limited for $8,179,179, taxes included. It was the lowest compliant bid in a public call for tenders that received three bids.
  • The council also authorized $817,917.89 for contingencies and $136,820.26 for related impacts, bringing the authorized total to $9,133,917.15, taxes included.
  • The City must assess Insituform’s performance. For each day the contractor is late finishing the work, it must pay a penalty of 0.1% of the contract price, excluding taxes and contingencies, and at least $1,000 per day.

What it means for you#

  • Residents in the borough: Sewer pipes on various streets are scheduled for work from April to October 2026. The supplied material does not name the streets or give a detailed traffic plan.
  • Taxpayers: The City centre will cover the full expense in its budget. City staff say part of the work is eligible for the TECQ24 subsidy and is funded at 98% under its agreement; the rest is at the taxpayer’s expense.
  • The contractor: Insituform must complete the work under the contract terms and may face daily late penalties.

Money#

The City authorized a maximum expense of $9,133,917.15, taxes included.

  • The total is budgeted under the City’s asset-management directorate and borrowing bylaw 22-046. The amount after tax rebates is $8,340,483.82.
  • The council approved the contingency and related-impact budgets as part of the total. The supplied material does not give a separate amount for the TECQ24 subsidy.

What is unclear#

  • The decision summary says a street list and traffic information are attached, but those attachments were not supplied here.
  • The exact amount and share of costs covered by TECQ24 are not stated.
  • The supplied material does not explain what would trigger use of the contingency and related-impact budgets, or how unused amounts would be handled.

Case for#

  • City staff say lining can renew pipes faster and at lower cost than excavation, with less disruption to nearby infrastructure and traffic.
  • The lowest compliant bid was 8.84% below the City’s estimate. Three firms bid.
  • City staff say lining also reduces excavated soil and greenhouse-gas emissions compared with excavation.

Case against#

  • The council authorized nearly $954,738 beyond the contractor’s base price for contingencies and related impacts; the supplied material does not explain when those funds would be used.
  • Residents may face traffic or other disruptions during the work, but the supplied material does not provide the affected streets or detailed timing.